CN115929048A - Construction method for large-area special-shaped aluminum plate ceiling with irregular arc-shaped structure - Google Patents
Construction method for large-area special-shaped aluminum plate ceiling with irregular arc-shaped structure Download PDFInfo
- Publication number
- CN115929048A CN115929048A CN202211572150.0A CN202211572150A CN115929048A CN 115929048 A CN115929048 A CN 115929048A CN 202211572150 A CN202211572150 A CN 202211572150A CN 115929048 A CN115929048 A CN 115929048A
- Authority
- CN
- China
- Prior art keywords
- aluminum plate
- keel
- ceiling
- shaped
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 title claims abstract description 149
- 229910052782 aluminium Inorganic materials 0.000 title claims abstract description 149
- 238000010276 construction Methods 0.000 title claims abstract description 48
- 230000001788 irregular Effects 0.000 title claims abstract description 24
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 64
- 239000010959 steel Substances 0.000 claims abstract description 64
- 238000009434 installation Methods 0.000 claims abstract description 51
- 238000012545 processing Methods 0.000 claims abstract description 35
- 238000013461 design Methods 0.000 claims abstract description 20
- 230000035939 shock Effects 0.000 claims abstract description 19
- 238000000034 method Methods 0.000 claims abstract description 15
- 239000000463 material Substances 0.000 claims abstract description 14
- 238000012546 transfer Methods 0.000 claims abstract description 12
- 238000009413 insulation Methods 0.000 claims abstract description 4
- 238000003754 machining Methods 0.000 claims abstract 3
- 238000005259 measurement Methods 0.000 claims description 17
- 238000010586 diagram Methods 0.000 claims description 16
- 238000006243 chemical reaction Methods 0.000 claims description 14
- 239000004677 Nylon Substances 0.000 claims description 8
- 229920001778 nylon Polymers 0.000 claims description 8
- 238000013016 damping Methods 0.000 claims description 7
- 238000002955 isolation Methods 0.000 claims description 7
- 238000010521 absorption reaction Methods 0.000 claims description 6
- 238000004519 manufacturing process Methods 0.000 claims description 5
- 239000003292 glue Substances 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 claims description 4
- 238000005192 partition Methods 0.000 claims description 3
- 238000005452 bending Methods 0.000 claims description 2
- 230000000694 effects Effects 0.000 claims description 2
- 238000000638 solvent extraction Methods 0.000 claims 2
- 239000012634 fragment Substances 0.000 claims 1
- 238000007789 sealing Methods 0.000 claims 1
- 239000007921 spray Substances 0.000 claims 1
- 239000006096 absorbing agent Substances 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 5
- 238000007689 inspection Methods 0.000 description 5
- 238000004378 air conditioning Methods 0.000 description 4
- 230000008676 import Effects 0.000 description 2
- 238000000053 physical method Methods 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 239000000779 smoke Substances 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- GXPHKUHSUJUWKP-UHFFFAOYSA-N troglitazone Chemical compound C1CC=2C(C)=C(O)C(C)=C(C)C=2OC1(C)COC(C=C1)=CC=C1CC1SC(=O)NC1=O GXPHKUHSUJUWKP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及吊顶施工技术领域,更具体而言,涉及一种不规则弧形结构大面积异形铝板吊顶施工方法。The invention relates to the technical field of suspended ceiling construction, and more specifically relates to a construction method for a large-area special-shaped aluminum plate suspended ceiling with an irregular arc structure.
背景技术Background technique
随着人们审美观及对建筑品质的需求,对建筑外观及室内装饰提出了更高的艺术追求,多种类型的建筑艺术形态应运而生,建筑造型逐渐由矩形向各种不规则形状、弧形、曲线形转变。异形建筑室内吊顶通常有形状不规则、面积大、精度要求高等特点。With people's aesthetics and demand for architectural quality, higher artistic pursuits have been put forward for architectural appearance and interior decoration. Various types of architectural art forms have emerged as the times require, and architectural shapes have gradually changed from rectangles to various irregular shapes and arcs. shape, curve shape transformation. Indoor ceilings of special-shaped buildings usually have the characteristics of irregular shape, large area, and high precision requirements.
现有技术中,针对曲面不规则性吊顶,采用常规施工方法外观无法实现设计效果,勾搭式铝板的出现,在一定程度上改善了这一问题。勾搭式铝板单幅面积大,在管线密集、大型设备处无法按设计间距设置吊杆,且设备振动会造成铝板面变形,采用减隔震技术解决此问题。大面积异形铝板吊顶工程中存在测量定位困难,现场放大样耗时,大面积安装易晃动、脱落、错位,拼缝不顺直等问题;因此,对异形建筑铝板吊顶技术的研究显得尤为重要。In the prior art, in view of irregular curved surface ceilings, conventional construction methods cannot achieve design effects in appearance, and the emergence of hook-up aluminum plates has improved this problem to a certain extent. The hook-up aluminum plate has a large single-width area, and it is impossible to set the suspenders according to the designed spacing in places with dense pipelines and large-scale equipment, and the vibration of the equipment will cause deformation of the aluminum plate surface. The shock-absorbing and isolation technology is used to solve this problem. In the large-area special-shaped aluminum ceiling project, there are difficulties in measurement and positioning, time-consuming on-site sample enlargement, large-area installation is easy to shake, fall off, misplaced, and the joints are not straight. Therefore, the research on special-shaped building aluminum ceiling technology is particularly important.
发明内容Contents of the invention
为克服上述现有技术中存在的不足,本发明提供了一种不规则弧形结构大面积异形铝板吊顶施工方法。该施工方法实现了隔声降噪的目的,采用BIM+放线机器人+三维激光扫描实现铝板精准加工及安装,保证了大面积异形铝板安装的施工质量,提高了铝板安装的进度和一次合格率。In order to overcome the deficiencies in the above-mentioned prior art, the present invention provides a construction method for a large-area special-shaped aluminum plate ceiling with an irregular arc structure. This construction method achieves the purpose of sound insulation and noise reduction. BIM+laying robot+3D laser scanning is used to realize the precise processing and installation of aluminum plates, which ensures the construction quality of large-area special-shaped aluminum plate installations, and improves the progress and first pass rate of aluminum plate installation.
为解决上述技术问题,本发明采取的技术方案为:In order to solve the problems of the technologies described above, the technical scheme that the present invention takes is:
一种不规则弧形结构大面积异形铝板吊顶施工方法,包括以下步骤:A construction method for a large-area special-shaped aluminum plate ceiling with an irregular arc structure, comprising the following steps:
S1、实体测量;S1. Physical measurement;
S2、BIM深化设计,绘制排版图,绘制铝板加工图;S2. BIM deepens the design, draws layout drawings, and draws aluminum plate processing drawings;
S3、制定材料加工计划;S3. Make a material processing plan;
S4、型钢转换层施工;S4. Construction of section steel transfer layer;
S5、管线密集区域及大型设备下方隔震处理;S5. Seismic isolation treatment in pipeline-intensive areas and below large equipment;
S6、主次龙骨定位;S6, primary and secondary keel positioning;
S7、管线敷设、末端设备初就位;S7. Pipeline laying and initial installation of terminal equipment;
S8、铝板安装;S8, aluminum plate installation;
S9、活动式检修口、设备安装。S9, movable inspection port, equipment installation.
所述步骤S1中,测量采用三维扫描仪对现场已完成的主体、砌体结构,管道实体进行扫描,进行三维数据采集,捕捉的真实数据与BIM模型整合。In the step S1, the measurement uses a three-dimensional scanner to scan the completed main body, masonry structure, and pipeline entities on site to collect three-dimensional data, and integrate the captured real data with the BIM model.
步骤S2中,将整合完各专业的BIM模型图导入测量放线机器人中,并结合抄设的基准点完成吊顶控制线、边龙骨控制线、吊杆位置、0.5m标高线的测设,吊顶控制线测设在墙面及地面上,依据主控制线放出不同异形区域控制线的测设。In step S2, import the integrated BIM model diagrams of various disciplines into the surveying and setting-out robot, and complete the measurement and design of the ceiling control line, side keel control line, boom position, and 0.5m elevation line in combination with the reference points copied and set. The control line is measured and set on the wall and the ground, and the control line of different special-shaped areas is released according to the main control line.
步骤S2中,绘制排版图:BIM模型建模完成后对铝板进行分区分块编号,在策划时明确铝板安装的顺序,标注在BIM模型图及设计图纸中;In step S2, draw the typesetting diagram: after the BIM model modeling is completed, the aluminum panels are partitioned and numbered, and the order of aluminum panel installation is specified during planning, and marked in the BIM model diagram and design drawings;
绘制铝板加工图:按不同区域,区域内不同板块形状分别绘制不同的铝板加工图,并分区块出图,标明加工的先后顺序,在图纸中应表面铝板加工的部位,需要开洞或开孔的位置,铝板开洞加固形式,铝板尺寸加工所需的数据,加工尺寸误差控制在0.5mm以内。Draw aluminum plate processing diagrams: draw different aluminum plate processing drawings according to different regions and different plate shapes in the region, and draw out the drawings in sub-blocks to indicate the sequence of processing. In the drawings, the parts that should be surface aluminum plate processing need to be opened or opened The position of the aluminum plate, the form of opening and reinforcement of the aluminum plate, the data required for the size processing of the aluminum plate, and the error of the processing size is controlled within 0.5mm.
步骤S3中,在BIM模型中将需要加工的铝板生产材料加工清单,并注明相关的参数信息,形成铝板加工计划表,按区域铝板编号顺序整理;In step S3, in the BIM model, list the aluminum plate production materials that need to be processed, and indicate the relevant parameter information, to form an aluminum plate processing schedule, and organize them in the order of regional aluminum plate numbers;
编制材料加工计划根据勾搭铝板板块编号图,整理提料单,提料单中铝板顺序和现场计划安装的顺序一致。Compile the material processing plan according to the numbering diagram of the aluminum plates, sort out the bill of lading, and the order of the aluminum plates in the bill of lading is consistent with the order of the on-site planned installation.
步骤S4中,对空心楼盖板吊顶、吊杆长度大于2500mm时设置型钢转换层;吊顶型钢转换层形成井字形框架体系,边缘距墙200mm设置角钢边框,转换层纵横向龙骨的布置按空心楼盖板肋梁位置设置。In step S4, when the suspended ceiling of the hollow floor slab and the length of the suspender are greater than 2500mm, a section steel transfer layer is set; the ceiling section steel transfer layer forms a well-shaped frame system, and the edge is 200mm away from the wall. Cover rib beam position setting.
步骤S5中,部位吊杆间间距超过规范1200mm,局部位置与吊顶综合支架距离近,施工时采用隔震减震做法,在设备运行振动时不会影响吊顶的安全,为此该部位采用方钢上设橡胶减震垫减震,并在两侧吊杆上设置微型减震装置。In step S5, the distance between the suspenders exceeds the specification of 1200mm, and the distance between the partial position and the integrated support of the ceiling is close. The method of vibration isolation and shock absorption is adopted during construction, so that the safety of the ceiling will not be affected when the equipment vibrates. For this reason, square steel is used for this part There is a rubber shock-absorbing pad on the top for shock-absorbing, and micro-shock-absorbing devices are installed on the suspension rods on both sides.
步骤S6中,主次龙骨定位、安装包括以下步骤:In step S6, the primary and secondary keel positioning and installation include the following steps:
步骤一:在型钢转换层上按设计图纸定位主龙骨吊杆位置,吊杆长度统一,在挂接件上调节螺母实现对吊杆高度的微调;吊筋底部设置减震装置,挂接件、吊杆、减震装置组装完成后,将挂接件安装到型钢转换层上,然后安装轻钢主龙骨;Step 1: Locate the position of the main keel suspender on the section steel conversion layer according to the design drawings, the length of the suspender is uniform, and adjust the nut on the hanger to realize the fine adjustment of the height of the suspender; set the shock absorber at the bottom of the hanger, the hanger, After the suspenders and shock absorbing devices are assembled, install the hooks on the section steel conversion layer, and then install the light steel main keel;
步骤二:主龙骨安装就位后按标高线对主龙骨进行调平,对过长的龙骨为防止中部受弯变形出现向下的弧形,做预起拱处理,沿短跨起拱,对于不规则异形区域铝板吊顶,不宜起拱,按照统一标高进行调平处理,在吊顶高度下适当位置架设绿光红外线水平仪,调节轻钢主龙骨及螺母,使轻钢主龙骨标高一致,处于一个水平面,吊杆螺纹外露长度不少于3个完整丝扣;轻钢主龙骨端头吊点距主龙骨边缘不应大于300mm,端排吊点距侧墙间距不应大于200mm;次龙骨采用挂接件与主龙骨连接,边龙骨安装在房间四周围护结构上,下边缘与标准线平齐,选用膨胀螺栓等固定,间距不宜大于500mm,端头不宜大于50mm。Step 2: After the main keel is installed in place, level the main keel according to the elevation line. For the overly long keel, in order to prevent the middle part from being bent and deformed and appear downward arc, do pre-arching treatment, and arch along the short span. Aluminum plate ceilings in irregular and special-shaped areas are not suitable for arching. Leveling is carried out according to the uniform elevation. A green light infrared level is installed at an appropriate position under the ceiling height, and the light steel main keel and nuts are adjusted to make the light steel main keel have the same elevation and be on a horizontal plane. , the exposed length of the suspender thread is not less than 3 complete threaded buttons; the lifting point at the end of the light steel main keel should not be greater than 300mm from the edge of the main keel, and the distance between the end row of lifting points and the side wall should not be greater than 200mm; the secondary keel should be articulated The parts are connected with the main keel, the side keel is installed on the surrounding protection structure of the room, the lower edge is flush with the standard line, and fixed with expansion bolts, the spacing should not be greater than 500mm, and the end should not be greater than 50mm.
步骤S7中,主次轻钢龙骨安装完成后根据BIM排版图找准末端设备的位置,预先将管线布设到位及末端设备的连接线甩到相应位置。In step S7, after the primary and secondary light steel keels are installed, the position of the terminal equipment is identified according to the BIM layout drawing, and the pipelines are laid in place and the connecting lines of the terminal equipment are thrown to the corresponding positions in advance.
步骤S8中,吊顶安装采用整体定位+分区控制的方法,采用测量放线机器人配合测量工具完成控制线及点位的测设,确定施工的先后顺序,明确内控要求,避免各区块独立定位造成交接部位无法衔接,产生较大的偏差;In step S8, the installation of the suspended ceiling adopts the method of overall positioning + partition control, and the measurement and setting-out robot is used to cooperate with the measurement tools to complete the measurement and design of control lines and points, determine the sequence of construction, clarify internal control requirements, and avoid handover caused by independent positioning of each block The parts cannot be connected, resulting in a large deviation;
应选择区块集中部位,选择异形铝板或各区块连通的最长铝板作为铝板吊顶安装的起始段,依据总控制线及区块控制线确定起始铝板安装的边线,并在两侧或中间部位增设固定件,确保起始铝板定位后不左右移动,中间区域铝板纵横向拉尼龙线,形成十字交错的控制线;The centralized part of the block should be selected, and the special-shaped aluminum plate or the longest aluminum plate connected to each block should be selected as the initial section of the aluminum plate ceiling installation. Fixing parts are added to the position to ensure that the initial aluminum plate does not move left and right after positioning, and the aluminum plate in the middle area pulls the nylon line vertically and horizontally to form a cross-staggered control line;
起始铝板吊顶主空鼓固定:将起始龙骨牢固的固定在型钢转换层支架上,调整挂接件上螺母使其与转换层支架顶紧,并在纵横向主龙骨处做斜向龙骨进行加强,确保轻钢主龙骨固定到位不发生移动,固定间距不大于2m,使其形成一个牢固的龙骨骨架;Fix the main hollow of the starting aluminum plate ceiling: firmly fix the starting keel on the steel transfer layer bracket, adjust the nut on the hook to make it tight with the conversion layer bracket, and make oblique keels at the vertical and horizontal main keels. Reinforcement to ensure that the light steel main keel is fixed in place and does not move, and the fixing distance is not greater than 2m, so that it forms a firm keel skeleton;
以起始板固定牢固的龙骨为基准,依次安装其他轻钢主龙骨,并纵横向安装5-6块后对照定位线进行检查,看是否和尼龙线对齐;对齐后,安装侧龙骨;轻钢次龙骨安装前,应在轻钢主龙骨上标出吊顶铝板安装起始板的位置,并采用燕尾丝将起始板固定在次龙骨上,调整到位后,形成初始铝板安装单元,以此为基准块进行其它铝板的安装;依次向两端进行铝板的安装,安装时只需要把次龙骨挂接在主龙骨上,勾搭式铝板挂接在轻钢次龙骨上,勾搭式铝板与铝板之间采用卡接件连接,缝隙间封闭防震胶密封;Based on the firmly fixed keel of the starting plate, install other light steel main keels in sequence, and check against the positioning line after installing 5-6 pieces vertically and horizontally to see if it is aligned with the nylon line; after alignment, install the side keel; light steel Before the installation of the secondary keel, the position of the starting plate for the ceiling aluminum plate installation should be marked on the light steel main keel, and the starting plate should be fixed on the secondary keel with dovetail wires. The reference block is used to install other aluminum plates; the aluminum plates are installed at both ends in turn. During installation, the secondary keel is only needed to be hung on the main keel, and the hook-type aluminum plate is hung on the light steel secondary keel. Between the hook-type aluminum plate and the aluminum plate It is connected by clamping parts, and the gaps are sealed with anti-vibration glue;
对于带灯具孔、消防喷淋孔、空调风口、广播等洞口的铝板安装时,相关专业人员应与吊顶作业人员配合,及时将末端设备固定到位,如无法及时固定设备时,应将电源线、网线、电线、信号线等及时从铝板开始的孔洞引出,并对照BIM图纸,实现精准引出;When installing aluminum panels with openings such as lamp holes, fire sprinkler holes, air-conditioning outlets, and broadcasting, relevant professionals should cooperate with ceiling operators to fix the terminal equipment in place in time. If the equipment cannot be fixed in time, the power cord, Network cables, wires, signal lines, etc. are drawn out from the holes in the aluminum plate in time, and compared with the BIM drawings, to achieve precise lead out;
铝板安装时采用已字形龙骨卡入主龙骨上,铝板与铝板之间采用卡接件紧固,起到精准定位及锁紧的作用。When the aluminum plate is installed, the zigzag keel is used to snap into the main keel, and the aluminum plate is fastened with clips to play the role of precise positioning and locking.
与现有技术相比,本发明所具有的有益效果为:Compared with prior art, the beneficial effect that the present invention has is:
本发明提出的不规则弧形结构大面积异形铝板吊顶施工方法解决了异形结构复杂空间大面积吊顶与管线综合定位精准度差的问题,改变了从结构中间位置及一端为起点安装铝板的做法,实现了多点作业,整体拼装,减少了地面及顶面放大样、对齐、校正等所消耗的时间,解决了大面积铝板易晃动、脱落、错位、拼缝不顺直等问题。在管线密集及大型设备下方采用方钢管、收缩减震条、螺杆、自制减震器组成吊顶支架,减少设备针对对吊顶的影响,实现了隔声降噪的目的,采用BIM+放线机器人+三维激光扫描实现铝板精准加工及安装,保证了大面积异形铝板安装的施工质量,提高了铝板安装的进度和一次合格率。The construction method of large-area special-shaped aluminum plate ceiling with irregular arc structure proposed by the present invention solves the problem of poor comprehensive positioning accuracy of large-area ceiling and pipeline in complex space with special-shaped structure, and changes the method of installing aluminum plate starting from the middle position and one end of the structure. It realizes multi-point operation and overall assembly, reduces the time consumed for enlargement, alignment, and calibration of the ground and top surfaces, and solves the problems of large-area aluminum plates that are easy to shake, fall off, misplaced, and seams are not straight. Under dense pipelines and large equipment, square steel pipes, shrinkage damping strips, screws, and self-made shock absorbers are used to form ceiling brackets to reduce the impact of equipment on the ceiling and achieve the purpose of sound insulation and noise reduction. BIM + wire-releasing robot + 3D Laser scanning realizes precise processing and installation of aluminum plates, ensures the construction quality of large-area special-shaped aluminum plates, and improves the progress and first-time pass rate of aluminum plate installations.
本方法采用三维激光扫描仪对现场实体进行扫描,运用BIM软件对异形结构铝板吊顶进行综合排布,并明确不同区域铝板加工、安装的顺序,对铝板进行编号避免混乱影响安装进度,编号后由厂家按照料单进行批量化生产,在生产中按区域分批制作;所有末端灯具、喷淋头、风口、检修口等全部在工厂加工成型,并做加固处理。采用本施工方法可提高加工及安装的速度及现场安装的精度,缩短施工周期,降低综合施工成本。This method uses a three-dimensional laser scanner to scan the on-site entity, uses BIM software to comprehensively arrange the aluminum plate ceiling with special-shaped structures, and defines the order of aluminum plate processing and installation in different areas, and numbers the aluminum plates to avoid confusion and affect the installation progress. The manufacturer conducts mass production according to the bill of materials, and makes batches by area during production; all terminal lamps, sprinklers, tuyere, inspection ports, etc. are all processed in the factory and reinforced. Adopting the construction method can improve the speed of processing and installation and the precision of on-site installation, shorten the construction period, and reduce the comprehensive construction cost.
本方法利用测量机器人对不同结构形状区域铝板吊顶按BIM排版图进行分区定位,每个区采用尼龙线进行细部精准定位,在每个区域吊顶中间位置固定起始端安装单元,在搭板的一侧设置用于挂接的板与板的卡环,采用专用扣接件将两板之间实现简易连接,实现了不规则弧形结构勾搭式铝板区块间吊顶从中间向四边安装的目的;本方法采用BIM+测量放线机器人对吊顶区块整体定位,分块控制的施工方法,在吊杆与主龙骨连接部位设置减隔震装置,吊顶板一层设置用于挂接的卡环,吊顶板减震收口技术安装勾搭式铝板,具有施工速度快、施工精度高、专业间配合快、操作安全性高等优点,可实现分项工程一次成优的目的。In this method, the measurement robot is used to locate the aluminum plate ceilings in different structural shapes according to the BIM layout diagram. Each area uses nylon wires for detailed positioning, and the initial installation unit is fixed in the middle of the ceiling in each area, and on the side of the board. Set the clasp rings for the articulated boards and boards, and use special fasteners to realize simple connection between the two boards, realizing the purpose of installing the ceiling from the middle to the four sides of the hook-up aluminum board block with irregular arc structure; Methods BIM+ surveying and laying-out robot is used to locate the ceiling block as a whole, and the construction method is controlled by blocks. The vibration-absorbing and isolating device is installed at the connection part between the suspender and the main keel. The shock-absorbing closure technology installs the hook-up aluminum plate, which has the advantages of fast construction speed, high construction precision, fast inter-professional cooperation, high operational safety, etc., and can achieve the goal of a sub-project to be completed at one time.
本方法适用于铝板吊顶施工,特别是异形结构大空间勾搭式铝板吊顶安装优势较明显;采用本施工方法有效控制铝板施工安装质量,并充分考虑设备振动对铝板及其龙骨的影响,采取了减隔震设计,施工质量满足规范要求,加之采用BIM技术进行优化设计使末端设备做到了成排成线,达到了创优标准;在质量、安全、进度、环保等方面均取得了良好的效果,具有较高的使用和推广价值。This method is suitable for the construction of aluminum plate ceilings, especially the installation advantages of special-shaped large-space hook-up aluminum plate ceilings are obvious; this construction method can effectively control the quality of aluminum plate construction and installation, and fully consider the impact of equipment vibration on aluminum plates and their keels. The seismic isolation design and construction quality meet the requirements of the code, and the optimized design using BIM technology enables the terminal equipment to be lined up, reaching the standard of excellence; good results have been achieved in terms of quality, safety, progress, and environmental protection. It has high use and promotion value.
附图说明Description of drawings
图1为本发明工艺流程图;Fig. 1 is a process flow diagram of the present invention;
图2为勾搭式铝板吊顶示意图;Figure 2 is a schematic diagram of a hook-up aluminum ceiling;
图3为图2中A处放大图;Figure 3 is an enlarged view of A in Figure 2;
图4为本发明中微型减震装置示意图;Fig. 4 is a schematic diagram of a miniature damping device in the present invention;
图5为管线密集区域、大型设备下方吊顶龙骨及减隔震装置示意图;Figure 5 is a schematic diagram of the pipeline-intensive area, the ceiling keel under the large equipment, and the shock-absorbing and isolating device;
图6为大型设备下方减震示意图。Figure 6 is a schematic diagram of shock absorption under large equipment.
具体实施方式Detailed ways
为了能够更清楚地理解本发明的上述目的、特征和优点,下面结合附图和具体实施例对本发明进行进一步的详细描述。需要说明的是,在不冲突的情况下,本申请的实施例及实施例中的特征可以相互组合。In order to more clearly understand the above objects, features and advantages of the present invention, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that, in the case of no conflict, the embodiments of the present application and the features in the embodiments can be combined with each other.
在下面的描述中阐述了很多具体细节以便于充分理解本发明,但是,本发明还可以采用其他不同于此描述的方式来实施,因此,本发明的保护范围并不受下面公开的具体实施例的限制。In the following description, many specific details are set forth in order to fully understand the present invention. However, the present invention can also be implemented in other ways than this description. Therefore, the protection scope of the present invention is not limited by the specific embodiments disclosed below. limits.
如图1至图5所示,不规则弧形结构大面积异形铝板吊顶施工方法,包括转换层支架,支架下设置吊顶吊杆,所述吊顶吊杆遇管线密集部位及大型设备处设置减隔震装置,底部减隔震装置底端为方钢,方钢上粘结橡胶减震垫,吊杆上设置由橡胶圈、垫片、螺母、U型挂件组成的微型减震装置。减震装置与U型轻钢主龙骨连接,轻钢主龙骨与次龙骨采用挂接件连接,勾搭板挂接在次龙骨上,板之间缝隙采用防震胶密封。As shown in Figures 1 to 5, the construction method of large-area special-shaped aluminum plate ceilings with irregular arc structures includes transfer layer supports, and ceiling suspenders are installed under the supports, and the ceiling suspenders are equipped with space-reducing parts where pipelines are densely populated and large equipment. The bottom end of the shock absorbing and isolating device is a square steel, and the rubber shock absorbing pad is bonded to the square steel. A miniature shock absorbing device composed of rubber rings, gaskets, nuts, and U-shaped pendants is installed on the boom. The shock absorbing device is connected with the U-shaped light steel main keel, the light steel main keel and the secondary keel are connected by hooks, the hook plate is hung on the secondary keel, and the gap between the plates is sealed with shockproof glue.
施工方法包括以下步骤:The construction method includes the following steps:
实体测量;physical measurement;
BIM深化设计,绘制排版图,绘制铝板加工图;BIM deepens the design, draws layout drawings, and draws aluminum plate processing drawings;
制定材料加工计划;Make material processing plan;
型钢转换层施工;Steel transfer layer construction;
管线密集区域及大型设备下方隔震处理;Seismic isolation treatment in pipeline-intensive areas and under large equipment;
主次龙骨定位;Primary and secondary keel positioning;
管线敷设、末端设备初就位;Pipeline laying and initial installation of terminal equipment;
铝板安装;Aluminum plate installation;
活动式检修口、设备安装。Movable inspection port, equipment installation.
优选的,所述实体测量包括以下步骤:Preferably, said entity measurement comprises the following steps:
三维扫描:采用三维扫描仪对现场已完成的主体、砌体结构,管道实体进行扫描,进行三维数据采集,捕捉的真实数据与BIM模型整合。3D scanning: use a 3D scanner to scan the completed main body, masonry structure, and pipeline entities on site, collect 3D data, and integrate the captured real data with the BIM model.
BIM深化设计:掌握设计图纸中所反映的材质、色彩、分格等参数,充分了解设计意图。并对拟选用的铝板生产厂家设备及产品进行考察。在真实BIM模型图上按照各设备专业施工图结合照明、通风空调、弱电、消防、信号等专业的需求,合理优化风口、照明灯具、消防及弱电广播、喷淋、烟感、检修口等末端设备的位置,在符合规范间距及照明亮度的前提下,做到成排成线,弧度一致,所有设备应做到居于板中,局部位置要做到对称,统一。龙骨的排布宜与空调通风系统的风口、灯具、喷淋头、检修孔、监测、升降投影仪等设备设施的排布位置错开,不宜切断主龙骨。BIM in-depth design: master the parameters such as material, color, and grid reflected in the design drawings, and fully understand the design intent. And inspect the equipment and products of the aluminum plate manufacturers to be selected. On the real BIM model drawing, in accordance with the professional construction drawings of each equipment and combined with the professional needs of lighting, ventilation and air conditioning, weak current, fire protection, signal, etc., rationally optimize the terminals such as air outlets, lighting fixtures, fire protection and weak current broadcasting, spraying, smoke detectors, and inspection ports The location of the equipment, under the premise of conforming to the standard spacing and lighting brightness, should be in rows and lines with consistent arcs. All equipment should be located in the board, and the local positions should be symmetrical and unified. The layout of the keel should be staggered with the arrangement of air outlets, lamps, sprinklers, inspection holes, monitoring, lifting projectors and other equipment and facilities of the air conditioning and ventilation system, and it is not suitable to cut off the main keel.
模型输出及测量放样:将整合完各专业的BIM模型图导入测量放线机器人中,并结合抄设的基准点完成吊顶控制线、边龙骨控制线、吊杆位置、0.5m标高线的测设。吊顶控制线应测设在墙面及地面上,依据主控制线放出不同异形区域控制线的测设。Model output and measurement and setting out: import the integrated BIM model drawings of various disciplines into the measuring and setting out robot, and complete the measurement and design of the ceiling control line, side keel control line, boom position, and 0.5m elevation line in combination with the reference points copied and set . The control line of the ceiling should be measured and set on the wall and the ground, and the control line of different special-shaped areas should be measured and set according to the main control line.
绘制排版图:BIM模型建模完成后应对铝板进行分区分块编号,在策划时就应明确铝板安装的顺序,标注在BIM模型图及设计图纸中。Draw the typesetting diagram: After the BIM model modeling is completed, the aluminum panels should be partitioned and numbered. When planning, the order of aluminum panel installation should be clarified and marked in the BIM model diagram and design drawings.
绘制铝板加工图:按不同区域,区域内不同板块形状分别绘制不同的铝板加工图,并分区块出图,标明加工的先后顺序,在图纸中应表面铝板加工的部位,需要开洞或开孔的位置,铝板开洞加固形式,铝板尺寸等加工所需的数据,加工尺寸误差控制在0.5mm以内。Draw aluminum plate processing diagrams: draw different aluminum plate processing drawings according to different regions and different plate shapes in the region, and draw out the drawings in sub-blocks to indicate the sequence of processing. In the drawings, the parts that should be surface aluminum plate processing need to be opened or opened The position of the aluminum plate, the form of reinforcement of the opening of the aluminum plate, the size of the aluminum plate and other data required for processing, the error of the processing size is controlled within 0.5mm.
在BIM模型中将需要加工的铝板生产材料加工清单,并注明相关的参数信息,形成铝板加工计划表。应按区域铝板编号顺序整理,In the BIM model, the processing list of the aluminum plate production materials that need to be processed is made, and the relevant parameter information is indicated to form the aluminum plate processing schedule. It should be sorted according to the order of regional aluminum plate numbers,
编制材料加工计划根据勾搭铝板板块编号图,整理提料单,提料单中铝板顺序应和现场计划安装的顺序一致。Compile the material processing plan according to the numbering diagram of the aluminum plates, sort out the bill of lading, and the order of the aluminum plates in the bill of lading should be consistent with the order of the on-site planned installation.
型钢转换层施工:对空心楼盖板吊顶、吊杆长度大于2500mm应设置型钢转换层。吊顶型钢转换层应形成井字形框架体系,边缘距墙200mm设置角钢边框,转换层纵横向龙骨的布置应按空心楼盖板肋梁位置设置。Construction of section steel transfer floor: for the ceiling of hollow floor slabs and the length of suspenders greater than 2500mm, a section steel transfer floor should be set. The steel transfer floor of the suspended ceiling should form a well-shaped frame system, and the edge should be set with an angle steel frame 200mm away from the wall.
管线密集区域及大型设备下方隔震处理;该部位吊杆间间距超过规范1200mm,局部位置与吊顶综合支架距离较近,施工时采用隔震减震做法,在设备运行振动时不会影响吊顶的安全,为此该部位采用方钢上设橡胶减震垫减震,并在两侧吊杆上设置由橡胶圈、垫片、螺母、U型挂件组成的微型减震装置。Seismic isolation treatment in areas with dense pipelines and under large-scale equipment; the distance between suspenders in this part exceeds the specification of 1200mm, and the distance between the partial position and the integrated support of the ceiling is relatively close. Safety, for this reason, this part adopts rubber damping pads on the square steel for shock absorption, and a miniature damping device composed of rubber rings, gaskets, nuts, and U-shaped pendants is set on the suspenders on both sides.
主次龙骨定位、安装包括以下步骤:Primary and secondary keel positioning and installation include the following steps:
步骤一:在型钢转换层上按设计图纸定位主龙骨吊杆位置,吊杆长度统一,在挂接件上调节螺母实现对吊杆高度的微调;吊筋底部设置减震装置,减震装置由U形状件、弹簧、一字型钢板、橡胶圈、垫片、螺栓等组成。挂接件、吊杆、减震装置组装完成后,将挂接件安装到型钢转换层上,然后安装轻钢主龙骨。Step 1: Locate the position of the main keel suspender on the section steel conversion layer according to the design drawings, the length of the suspender is uniform, adjust the nut on the hook to realize the fine adjustment of the height of the suspender; install a shock absorber at the bottom of the hanger, and the shock absorber consists of Composed of U-shaped parts, springs, flat steel plates, rubber rings, gaskets, bolts, etc. After the hooks, hangers, and shock absorbers are assembled, install the hooks on the section steel conversion layer, and then install the light steel main keel.
步骤二:主龙骨安装就位后应按标高线对主龙骨进行调平,对过长的龙骨为防止中部受弯变形出现向下的弧形,做预起拱处理,沿短跨起拱,对于不规则异形区域铝板吊顶,不宜起拱,应按照统一标高进行调平处理,在吊顶高度下适当位置架设绿光红外线水平仪,调节轻钢主龙骨及螺母,使轻钢主龙骨标高一致,处于一个水平面,吊杆螺纹外露长度不应少于3个完整丝扣;轻钢主龙骨端头吊点距主龙骨边缘不应大于300mm,端排吊点距侧墙间距不应大于200mm。次龙骨采用挂接件与主龙骨连接,边龙骨安装在房间四周围护结构上,下边缘与标准线平齐,选用膨胀螺栓等固定,间距不宜大于500mm,端头不宜大于50mm。Step 2: After the main keel is installed in place, the main keel should be leveled according to the elevation line. For the overly long keel, in order to prevent the middle part from being bent and deformed and appear downward arc, do pre-arching treatment, and arch along the short span. For the aluminum plate ceiling in the irregular and special-shaped area, it is not suitable to arch, and it should be leveled according to the uniform elevation. Set up a green light infrared level at an appropriate position under the height of the ceiling, and adjust the light steel main keel and nuts to make the light steel main keel consistent. On a horizontal plane, the exposed length of the suspender thread should not be less than 3 complete threads; the lifting point at the end of the light steel main keel should not be greater than 300mm from the edge of the main keel, and the distance between the end row of lifting points and the side wall should not be greater than 200mm. The secondary keel is connected with the main keel by hooks, and the side keel is installed on the surrounding protection structure of the room. The lower edge is flush with the standard line, and fixed by expansion bolts. The spacing should not be greater than 500mm, and the end should not be greater than 50mm.
管线敷设、末端设备出就位:主次轻钢龙骨安装完成后根据BIM排版图找准末端设备的位置预先将管线布设到位及末端设备的连接线甩到相应位置。Pipeline laying and terminal equipment in place: After the primary and secondary light steel keels are installed, find out the position of the terminal equipment according to the BIM layout drawing, and pre-lay the pipelines in place and throw the connecting lines of the terminal equipment to the corresponding positions.
吊顶铝板安装包括以下步骤:The installation of suspended ceiling aluminum plate includes the following steps:
吊顶安装采用整体定位+分区控制的方法,采用测量放线机器人配合测量工具完成控制线及点位的测设,要确定施工的先后顺序,明确内控要求,避免各区块独立定位造成交接部位无法衔接,产生较大的偏差。The installation of the suspended ceiling adopts the method of overall positioning + partition control. The measurement and setting-out robot is used to cooperate with the measurement tools to complete the measurement and design of control lines and points. It is necessary to determine the sequence of construction, clarify internal control requirements, and avoid independent positioning of each block. The handover parts cannot be connected , resulting in a large deviation.
应选择区块相对集中部位,尽可能选择异形铝板或各区块连通的最长铝板作为铝板吊顶安装的起始段,依据总控制线及区块控制线确定起始铝板安装的边线,并在两侧或中间部位增设固定件,确保起始铝板定位后不左右移动,中间区域铝板纵横向拉尼龙线,形成十字交错的控制线,尼龙线不易过长,过长会出现变形、下挠等现象。The relatively concentrated part of the block should be selected, and the special-shaped aluminum plate or the longest aluminum plate connected to each block should be selected as the initial section of the aluminum plate ceiling installation, and the edge line of the initial aluminum plate installation should be determined according to the general control line and the block control line. Fixing parts are added to the side or middle part to ensure that the initial aluminum plate does not move left and right after positioning. The aluminum plate in the middle area pulls the nylon wire vertically and horizontally to form a criss-cross control line. The nylon wire is not easy to be too long, and deformation and downward bending will occur if it is too long .
起始铝板吊顶主空鼓固定:应将起始龙骨牢固的固定在型钢转换层支架上,调整挂接件上螺母使其与转换层支架顶紧,并在纵横向主龙骨处做斜向龙骨进行加强,确保轻钢主龙骨固定到位不发生移动,固定间距不大于2m,使其形成一个牢固的龙骨骨架。Fix the main hollow of the starting aluminum plate ceiling: the starting keel should be firmly fixed on the steel transfer layer bracket, adjust the nut on the hook to make it tight with the conversion layer bracket, and make oblique keels at the vertical and horizontal main keels Reinforce to ensure that the light steel main keel is fixed in place and does not move, and the fixing distance is not greater than 2m, so that it forms a strong keel skeleton.
以起始板固定牢固的龙骨为基准,依次安装其他轻钢主龙骨,并纵横向安装5-6块后对照定位线进行检查,看是否和尼龙线对齐;对齐后,安装侧龙骨;轻钢次龙骨安装前,应在轻钢主龙骨上标出吊顶铝板安装起始板的位置,并采用燕尾丝将起始板固定在次龙骨上,调整到位后,形成初始铝板安装单元,以此为基准块进行其它铝板的安装。依次向两端进行铝板的安装,安装时只需要把次龙骨挂接在主龙骨上,勾搭式铝板挂接在轻钢次龙骨上,勾搭式铝板与铝板之间采用卡接件连接,缝隙间封闭防震胶密封。Based on the firmly fixed keel of the starting plate, install other light steel main keels in sequence, and check against the positioning line after installing 5-6 pieces vertically and horizontally to see if it is aligned with the nylon line; after alignment, install the side keel; light steel Before the installation of the secondary keel, the position of the starting plate for the ceiling aluminum plate installation should be marked on the light steel main keel, and the starting plate should be fixed on the secondary keel with dovetail wires. The reference block is used for the installation of other aluminum plates. Install the aluminum plates to both ends in sequence. During installation, you only need to hang the secondary keel on the main keel. The hook-up aluminum plate is hung on the light steel secondary keel. The hook-up aluminum plate and the aluminum plate are connected by clips. Closure shockproof glue seal.
对于带灯具孔、消防喷淋孔、空调风口、广播等洞口的铝板安装时,相关专业人员应与吊顶作业人员配合,及时将末端设备固定到位,如无法及时固定设备时,应将电源线、网线、电线、信号线等及时从铝板开始的孔洞引出,并对照BIM图纸,实现精准引出。When installing aluminum panels with openings such as lamp holes, fire sprinkler holes, air-conditioning outlets, and broadcasting, relevant professionals should cooperate with ceiling operators to fix the terminal equipment in place in time. If the equipment cannot be fixed in time, the power cord, Network cables, electric wires, signal lines, etc. are led out from the holes in the aluminum plate in time, and are accurately drawn out according to the BIM drawings.
铝板安装时采用已字形龙骨卡入主龙骨上,铝板与铝板之间采用卡接件紧固,起到精准定位及锁紧的作用。When the aluminum plate is installed, the zigzag keel is used to snap into the main keel, and the aluminum plate is fastened with clips to play the role of precise positioning and locking.
上面仅对本发明的较佳实施例作了详细说明,但是本发明并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化,各种变化均应包含在本发明的保护范围之内。Only the preferred embodiments of the present invention have been described in detail above, but the present invention is not limited to the above-mentioned embodiments. Within the scope of knowledge possessed by those of ordinary skill in the art, various modifications can also be made without departing from the gist of the present invention. Various changes should be included within the protection scope of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211572150.0A CN115929048B (en) | 2022-12-08 | 2022-12-08 | A construction method for large-area special-shaped aluminum plate ceiling with irregular arc structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211572150.0A CN115929048B (en) | 2022-12-08 | 2022-12-08 | A construction method for large-area special-shaped aluminum plate ceiling with irregular arc structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN115929048A true CN115929048A (en) | 2023-04-07 |
| CN115929048B CN115929048B (en) | 2025-02-07 |
Family
ID=86650346
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211572150.0A Active CN115929048B (en) | 2022-12-08 | 2022-12-08 | A construction method for large-area special-shaped aluminum plate ceiling with irregular arc structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115929048B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117231003A (en) * | 2023-09-20 | 2023-12-15 | 中国建筑第八工程局有限公司 | Construction method of special-shaped perforated aluminum plate combined ceiling |
| CN117328603A (en) * | 2023-09-19 | 2024-01-02 | 浙江亚厦装饰股份有限公司 | A shock-absorbing ceiling structure suitable for low-rise and high-rise buildings and its installation method |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104912340A (en) * | 2015-06-09 | 2015-09-16 | 华鼎建筑装饰工程有限公司 | Construction method for double-curve triangular aluminum plate unit type hanging ceiling |
| WO2016033770A1 (en) * | 2014-09-04 | 2016-03-10 | 冯新林 | Method for construction of suspended rhombic aluminum veneer shading curtain wall for exhibition hall |
| JP2016169492A (en) * | 2015-03-11 | 2016-09-23 | 株式会社奥村組 | Fail-safe ceiling structure |
| KR101915982B1 (en) * | 2018-07-25 | 2018-11-07 | (주)삼우종합건축사사무소 | Prefabricated system ceiling of clean room with the variable height structure |
| CN208309960U (en) * | 2018-05-02 | 2019-01-01 | 辽宁悦利建设科技发展集团有限公司 | A kind of steady type ceiling joist construction for construction and decoration |
| CN111058640A (en) * | 2019-12-24 | 2020-04-24 | 中启胶建集团有限公司 | Construction process of special-shaped hollow aluminum veneer ceiling under steel truss |
| CN211396228U (en) * | 2019-12-04 | 2020-09-01 | 深圳市工大国际工程设计有限公司 | A damping soundproof ceiling structure |
| CN111709074A (en) * | 2020-06-04 | 2020-09-25 | 深圳广田集团股份有限公司 | Construction method for intelligently controlling large-space special-shaped curved surface based on BIM technology |
| CN113235800A (en) * | 2021-04-28 | 2021-08-10 | 浙江亚厦装饰股份有限公司 | Assembled bathroom suspended ceiling structure and installation mode thereof |
| CN113360993A (en) * | 2021-06-30 | 2021-09-07 | 浙江乔兴建设集团有限公司 | BIM technology-based construction method for large-area complex-modeling suspended ceiling |
-
2022
- 2022-12-08 CN CN202211572150.0A patent/CN115929048B/en active Active
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2016033770A1 (en) * | 2014-09-04 | 2016-03-10 | 冯新林 | Method for construction of suspended rhombic aluminum veneer shading curtain wall for exhibition hall |
| JP2016169492A (en) * | 2015-03-11 | 2016-09-23 | 株式会社奥村組 | Fail-safe ceiling structure |
| CN104912340A (en) * | 2015-06-09 | 2015-09-16 | 华鼎建筑装饰工程有限公司 | Construction method for double-curve triangular aluminum plate unit type hanging ceiling |
| CN208309960U (en) * | 2018-05-02 | 2019-01-01 | 辽宁悦利建设科技发展集团有限公司 | A kind of steady type ceiling joist construction for construction and decoration |
| KR101915982B1 (en) * | 2018-07-25 | 2018-11-07 | (주)삼우종합건축사사무소 | Prefabricated system ceiling of clean room with the variable height structure |
| CN211396228U (en) * | 2019-12-04 | 2020-09-01 | 深圳市工大国际工程设计有限公司 | A damping soundproof ceiling structure |
| CN111058640A (en) * | 2019-12-24 | 2020-04-24 | 中启胶建集团有限公司 | Construction process of special-shaped hollow aluminum veneer ceiling under steel truss |
| CN111709074A (en) * | 2020-06-04 | 2020-09-25 | 深圳广田集团股份有限公司 | Construction method for intelligently controlling large-space special-shaped curved surface based on BIM technology |
| CN113235800A (en) * | 2021-04-28 | 2021-08-10 | 浙江亚厦装饰股份有限公司 | Assembled bathroom suspended ceiling structure and installation mode thereof |
| CN113360993A (en) * | 2021-06-30 | 2021-09-07 | 浙江乔兴建设集团有限公司 | BIM technology-based construction method for large-area complex-modeling suspended ceiling |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117328603A (en) * | 2023-09-19 | 2024-01-02 | 浙江亚厦装饰股份有限公司 | A shock-absorbing ceiling structure suitable for low-rise and high-rise buildings and its installation method |
| CN117231003A (en) * | 2023-09-20 | 2023-12-15 | 中国建筑第八工程局有限公司 | Construction method of special-shaped perforated aluminum plate combined ceiling |
Also Published As
| Publication number | Publication date |
|---|---|
| CN115929048B (en) | 2025-02-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109614723B (en) | Comprehensive construction method based on BIM technology | |
| CN102146706B (en) | Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof | |
| WO2023272593A1 (en) | Bim-technology-based large-area complex-shape suspended ceiling construction method | |
| CN115929048A (en) | Construction method for large-area special-shaped aluminum plate ceiling with irregular arc-shaped structure | |
| CN202117202U (en) | Light steel keel partition wall structure adaptive to construction errors of building structure | |
| CN118390757B (en) | A construction method for installing decorative panels on large-span walls | |
| CN210486028U (en) | A plenum structure under the stand ladder | |
| CN113152860A (en) | Ceiling installation method based on bim | |
| CN113338518A (en) | Construction method of GRG material acoustic suspended ceiling in large-scale construction project | |
| JP3827431B2 (en) | Construction method of clean room building | |
| CN103821373A (en) | Ceiling hanging construction technology of light steel keel gypsum boards | |
| JP5972294B2 (en) | Module internal partition for structural frame building | |
| CN108716571A (en) | Adjustable machine electric line suspension and support and its application method | |
| CN113550599A (en) | A kind of hyperboloid zigzag GRG construction method | |
| CN115977279B (en) | A partition wall structure system and construction method thereof | |
| CN211499400U (en) | Suspended ceiling | |
| CN116791808A (en) | A large-span hyperbolic corrugated aluminum plate accurately positioned suspended ceiling and construction method | |
| CN205591394U (en) | Pin -connected panel aluminium system abatvoix wall | |
| CN115559537A (en) | Three-dimensional inclined plane modeling suspended ceiling and construction method thereof | |
| CN106760003B (en) | Fire blocking structure under raised floor and construction method thereof | |
| CN110872901A (en) | Anti-static floor laying construction process | |
| CN208474665U (en) | Adjustable machine electric line suspension and support | |
| CN206503384U (en) | Build static pressure cell structure | |
| CN204040284U (en) | A kind of stone material composite honeycomb board installation of ceiling system | |
| CN211523715U (en) | From gypsum board of taking access hole and furred ceiling structure thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |