CN115833203A - A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery - Google Patents

A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery Download PDF

Info

Publication number
CN115833203A
CN115833203A CN202211600444.XA CN202211600444A CN115833203A CN 115833203 A CN115833203 A CN 115833203A CN 202211600444 A CN202211600444 A CN 202211600444A CN 115833203 A CN115833203 A CN 115833203A
Authority
CN
China
Prior art keywords
energy storage
storage battery
power
load
time interval
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211600444.XA
Other languages
Chinese (zh)
Inventor
高振宇
潘御钦
施婧
黄帅
石国超
聂磊寅
胡倩
周晋雅
李于宝
陈忠华
江全元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Electric Power Design Institute Co ltd
Zhejiang University ZJU
Original Assignee
Hangzhou Electric Power Design Institute Co ltd
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Electric Power Design Institute Co ltd, Zhejiang University ZJU filed Critical Hangzhou Electric Power Design Institute Co ltd
Priority to CN202211600444.XA priority Critical patent/CN115833203A/en
Publication of CN115833203A publication Critical patent/CN115833203A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明公开了一种基于多时间区间最优潮流和储能电池的电网调峰方法。由于储能对缓解变压器过载的作用是双重的:一是它必须在过载时提供足够的发电,即放电能力。二是要有足够的备用能力,以适应可能出现的峰值负荷预测误差。本发明基于该基本思想,采用的技术方案为:计及发电机爬坡约束和发电功率约束,结合储能电站荷电状态约束和功率约束,建立基于多时段的最优潮流公式,提出了部分发电机退役后,储能电站参与调峰缓解变压器过载压力的储能电池运行策略。本发明构建了基于多时段的最优潮流模型,提出了储能电池参与调峰的运行策略,实现了对电网的调峰效果,并且缓解了燃煤机组退役时主变压器和线路过载的压力。

Figure 202211600444

The invention discloses a power grid peak regulation method based on multi-time interval optimal power flow and energy storage batteries. Since the role of energy storage in alleviating the overload of the transformer is two-fold: one is that it must provide sufficient power generation when overloaded, that is, discharge capacity. The second is to have sufficient reserve capacity to accommodate possible peak load forecast errors. Based on this basic idea, the technical solution adopted by the present invention is as follows: taking into account the constraints of generator ramping and power generation, combined with the constraints of state of charge and power of energy storage power stations, an optimal power flow formula based on multi-periods is established, and some After the generator is decommissioned, the energy storage power station participates in the energy storage battery operation strategy of peak regulation to alleviate the overload pressure of the transformer. The invention constructs an optimal power flow model based on multi-periods, proposes an operation strategy for energy storage batteries to participate in peak regulation, realizes the peak regulation effect on the power grid, and alleviates the overload pressure of main transformers and lines when coal-fired units are decommissioned.

Figure 202211600444

Description

一种基于多时间区间最优潮流和储能电池的电网调峰方法A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery

技术领域technical field

本发明属于电力系统中储能电站的调控技术领域,涉及一种基于多时间区间最优潮流和储能电池的电网调峰方法。The invention belongs to the technical field of regulation and control of energy storage power stations in electric power systems, and relates to a power grid peak regulation method based on multi-time interval optimal power flow and energy storage batteries.

背景技术Background technique

发电与负荷的功率平衡是电力系统安全运行的重要基础,但由于电网中燃煤火电机组逐渐退役,新能源装机容量快速增加,使得电网电源技术和电源结构迅速转变。在电力系统调度过程中,调峰问题面临多个难点:一是新能源迅猛发展导致电网峰谷差进一步加大。二是外来电大量增加削弱了电网调峰能力。三是燃煤火电机组退役增加变压器过载风险。The power balance between power generation and load is an important basis for the safe operation of the power system. However, due to the gradual retirement of coal-fired thermal power units in the power grid and the rapid increase in the installed capacity of new energy sources, the grid power supply technology and power structure have changed rapidly. In the power system dispatching process, the peak shaving problem faces several difficulties: First, the rapid development of new energy sources further increases the peak-to-valley difference of the power grid. Second, the large increase in external electricity has weakened the peak-shaving capability of the power grid. Third, the decommissioning of coal-fired thermal power units increases the risk of transformer overload.

储能是电力系统中进行有功吞吐、实现能量时间和空间转移的设备,可有效改善电源结构和调节能力。储能系统被广泛认为是现代电力系统规划、运行和控制中提供显著灵活性的一种有效方法。近年来,电化学储能电池成本的下降显著促进了储能电站的电网规模应用。Energy storage is a device in the power system that performs active processing and realizes energy time and space transfer, which can effectively improve the power structure and regulation capabilities. Energy storage systems are widely recognized as an effective way to provide significant flexibility in the planning, operation, and control of modern power systems. In recent years, the cost reduction of electrochemical energy storage batteries has significantly promoted the grid-scale application of energy storage power plants.

目前,储能技术作为智能电网技术的重要组成部分,由于其具有响应速度快、功率容量配置灵活且不依赖于选址、循环寿命高、环境友好等优点被广泛关注。电池储能最具潜力的应用是利用其能量双向流动的特性实现对负荷峰谷差的调节。At present, energy storage technology, as an important part of smart grid technology, has attracted widespread attention due to its advantages such as fast response, flexible power capacity configuration and independent of site selection, high cycle life, and environmental friendliness. The most potential application of battery energy storage is to use its energy bidirectional flow characteristics to realize the adjustment of the load peak-valley difference.

电池储能系统应用于削峰填谷的研究,从不同的研究角度切入均达到了负荷转移、平滑负荷波动的目的,可较好地应对调峰所面临的多个难点。因此,随着储能技术的发展,合理利用储能系统达到最优的削峰填谷作用效果将会是重点研究问题。The application of battery energy storage system in the research of peak shaving and valley filling has achieved the purpose of load transfer and smoothing load fluctuation from different research angles, and can better deal with many difficulties faced by peak shaving. Therefore, with the development of energy storage technology, rational use of energy storage systems to achieve the optimal effect of peak shaving and valley filling will be a key research issue.

发明内容Contents of the invention

本发明所要解决的技术问题是克服现有技术存在的缺陷,提供一种基于多时间区间最优潮流和储能电池的电网调峰方法。由于储能对缓解变压器过载的作用是双重的:一是它必须在过载时提供足够的发电,即放电能力。二是要有足够的备用能力,以适应可能出现的峰值负荷预测误差。本发明基于该基本思想,计及发电机爬坡约束和发电功率约束,结合储能电站荷电状态约束和功率约束,建立基于多时间区间的最优潮流公式,提出了部分发电机退役后,储能电站参与调峰缓解变压器过载压力的储能电池运行策略。实现了对电网的调峰效果并以负荷峰谷差率为指标验证了该方法的有效性。The technical problem to be solved by the present invention is to overcome the defects existing in the prior art, and provide a power grid peak regulation method based on multi-time interval optimal power flow and energy storage batteries. Since the role of energy storage in alleviating the overload of the transformer is two-fold: one is that it must provide sufficient power generation when overloaded, that is, discharge capacity. The second is to have sufficient reserve capacity to accommodate possible peak load forecast errors. Based on this basic idea, the present invention takes into account the constraints of generator ramping and power generation, combined with the constraints of state of charge and power of energy storage power stations, establishes an optimal power flow formula based on multiple time intervals, and proposes that after some generators are decommissioned, The energy storage power station participates in the peak load regulation to alleviate the overload pressure of the transformer and the energy storage battery operation strategy. The peak-shaving effect of the power grid is realized and the effectiveness of the method is verified by the load peak-to-valley difference rate index.

为此,本发明采用的技术方案如下:一种基于多时间区间最优潮流和储能电池的电网调峰方法,该方法包括如下步骤:For this reason, the technical scheme adopted by the present invention is as follows: a method for peak regulation of a power grid based on multi-time interval optimal power flow and energy storage batteries, the method comprising the following steps:

S1:采用时间序列分析法的自回归模型预测负荷和风力/太阳能的数据;S1: Autoregressive models using time series analysis to predict load and wind/solar data;

S2:基于控制需求得到一组前瞻时间区间,基于自回归模型的预测数据,为每个时间区间建立一个直流潮流,考虑发电机的爬坡约束和发电功率约束,结合储能的荷电状态约束和功率约束,以及传输线和变压器容量约束,综合发电机和储能电池出力,以变压器负载率超阈值时间区间数最少为目标函数,建立整体多时间区间最优潮流模型;S2: Obtain a set of forward-looking time intervals based on control requirements, establish a DC power flow for each time interval based on the forecast data of the autoregressive model, consider the ramping constraints of the generator and the constraints of the generated power, and combine the constraints of the state of charge of the energy storage And power constraints, as well as transmission line and transformer capacity constraints, integrated generator and energy storage battery output, with the minimum number of time intervals when the transformer load rate exceeds the threshold as the objective function, an overall multi-time interval optimal power flow model is established;

S3:求解所建立的整体多时间区间最优潮流模型,得到各时段储能电池组的功率输出情况,从而得到储能电池参与调峰的运行策略,并以负荷峰谷差率为指标对该模型的负荷波动范围调峰效果进行评估分析。S3: Solve the established overall multi-time interval optimal power flow model to obtain the power output of the energy storage battery pack at each time period, thereby obtaining the operation strategy for the energy storage battery to participate in peak regulation, and using the load peak-to-valley difference rate as an indicator to determine the The peak-shaving effect of the load fluctuation range of the model is evaluated and analyzed.

进一步地,所述的步骤S1具体为:使用现时的干扰和有限项过去的观测值来预测模型的现时值,将预测值用于建立前瞻性优化形式;Further, the step S1 is specifically: use current disturbances and past observations of limited items to predict the current value of the model, and use the predicted value to establish a forward-looking optimization form;

将历史负荷或风力/太阳能数据作为历史数据样本

Figure BDA0003997203750000021
的未来时段预测数据
Figure BDA0003997203750000022
表示为:Use historical load or wind/solar data as historical data samples
Figure BDA0003997203750000021
Forecast data for the future period of
Figure BDA0003997203750000022
Expressed as:

Figure BDA0003997203750000023
Figure BDA0003997203750000023

式中,

Figure BDA0003997203750000024
为自回归系数,其中i=0,1,2,3,…,p,p表示所选历史数据时刻数;k表示需预测的未来时刻;自回归系数通过历史数据构建线性方程组结合预测误差最小得到,X表示负荷或风力/太阳能,εt为一个白噪点。In the formula,
Figure BDA0003997203750000024
is the autoregressive coefficient, where i=0,1,2,3,...,p, p represents the number of selected historical data moments; k represents the future time to be predicted; the autoregressive coefficient constructs a linear equation system through historical data combined with prediction errors The minimum is obtained, X represents load or wind/solar energy, ε t is a white noise point.

进一步地,所述的步骤S2具体为:考虑一组前瞻时间区间ST={p+1,p+2,…,T0},其中每个时间区间t建立一个直流潮流,如式(2)所示:Further, the step S2 is specifically: consider a set of forward-looking time intervals S T ={p+1,p+2,...,T 0 }, where each time interval t establishes a DC power flow, as shown in formula (2 ) as shown:

Figure BDA0003997203750000025
Figure BDA0003997203750000025

式中,AG和AESS分别表示发电机和储能电池组的连接矩阵;

Figure BDA0003997203750000026
Figure BDA0003997203750000027
分别表示时间区间t下发电机、储能电池组和负载的功率;Bt和θt分别表示系统的导纳矩阵和节点电压相角在时间区间t下的虚部;In the formula, A G and A ESS respectively represent the connection matrix of the generator and the energy storage battery pack;
Figure BDA0003997203750000026
and
Figure BDA0003997203750000027
respectively represent the power of the generator, energy storage battery pack and load in the time interval t; B t and θ t respectively represent the admittance matrix of the system and the imaginary part of the node voltage phase angle in the time interval t;

首先,利用一组变量对储能电池组的荷电状态进行跟踪;变量Et与储能电池充放电功率的联系如式(3)所示;First, a set of variables is used to track the state of charge of the energy storage battery pack; the relationship between the variable E t and the charging and discharging power of the energy storage battery is shown in formula (3);

Figure BDA0003997203750000028
Figure BDA0003997203750000028

系统的功率平衡约束如式(4)所示;The power balance constraint of the system is shown in formula (4);

Figure BDA0003997203750000029
Figure BDA0003997203750000029

式中,Ng表示发电机的数量;

Figure BDA00039972037500000210
表示时间区间t下发电机i的功率;
Figure BDA00039972037500000211
Figure BDA00039972037500000212
分别表示时间区间t下的风力/太阳能出力和波动量;
Figure BDA00039972037500000213
表示时间区间t下的线损功率;
Figure BDA00039972037500000214
表示时间区间t下在j位置的负载功率,
Figure BDA0003997203750000031
分别表示时间区间t下储能电池组在j位置的放电和充电功率;where Ng represents the number of generators;
Figure BDA00039972037500000210
Indicates the power of generator i in the time interval t;
Figure BDA00039972037500000211
and
Figure BDA00039972037500000212
Respectively represent the wind/solar output and fluctuations in the time interval t;
Figure BDA00039972037500000213
Indicates the line loss power under the time interval t;
Figure BDA00039972037500000214
Indicates the load power at position j under time interval t,
Figure BDA0003997203750000031
Respectively represent the discharge and charge power of the energy storage battery pack at position j under the time interval t;

发电机的机组出力约束如下:The unit output constraints of the generator are as follows:

Figure BDA0003997203750000032
Figure BDA0003997203750000032

式中,

Figure BDA0003997203750000033
和PG分别表示发电机出力的上下限;In the formula,
Figure BDA0003997203750000033
and PG respectively represent the upper and lower limits of generator output;

对发电机考虑爬坡约束,如式(6)所示:Consider the climbing constraint for the generator, as shown in formula (6):

Figure BDA0003997203750000034
Figure BDA0003997203750000034

式中,RG

Figure BDA0003997203750000035
分别表示发电机爬坡的下限和上限;In the formula, R G and
Figure BDA0003997203750000035
Respectively represent the lower limit and upper limit of generator ramp;

储能电池组的功率约束包含储能电池运行约束和能量状态约束,其中运行约束如下式所示:The power constraints of the energy storage battery pack include energy storage battery operating constraints and energy state constraints, where the operating constraints are shown in the following formula:

Figure BDA0003997203750000036
Figure BDA0003997203750000036

Figure BDA0003997203750000037
Figure BDA0003997203750000037

Figure BDA0003997203750000038
Figure BDA0003997203750000038

式中,

Figure BDA0003997203750000039
Figure BDA00039972037500000318
分别表示时间区间t下储能电池组的放电和充电功率;
Figure BDA00039972037500000310
Figure BDA00039972037500000311
分别表示储能电池组的额定放电和充电功率;
Figure BDA00039972037500000312
Figure BDA00039972037500000313
分别表示时间区间t储能电池组的放电和充电状态,且皆为0-1变量,根据实际考虑的时间区间内发电机/储能电池的具体状态确定这两个参数的值;In the formula,
Figure BDA0003997203750000039
and
Figure BDA00039972037500000318
Respectively represent the discharge and charge power of the energy storage battery pack under the time interval t;
Figure BDA00039972037500000310
and
Figure BDA00039972037500000311
respectively represent the rated discharge and charge power of the energy storage battery pack;
Figure BDA00039972037500000312
and
Figure BDA00039972037500000313
Respectively represent the discharge and charge states of the energy storage battery pack in the time interval t, and both are 0-1 variables. The values of these two parameters are determined according to the specific state of the generator/energy storage battery in the actually considered time interval;

能量约束如下式所示;The energy constraints are shown in the following formula;

Figure BDA00039972037500000314
Figure BDA00039972037500000314

Figure BDA00039972037500000315
Figure BDA00039972037500000315

式中,

Figure BDA00039972037500000316
Figure BDA00039972037500000317
分别表示储能电池组的充电效率和放电效率;τ表示1到T之间的任意一个点;EMax表示储能电池组的最大容量;E0表示储能电池组在所选时间周期中初始时刻的能量状态,时间周期由T个时间区间构成;T表示所选时间区间总数;In the formula,
Figure BDA00039972037500000316
and
Figure BDA00039972037500000317
Respectively represent the charging efficiency and discharge efficiency of the energy storage battery pack; τ represents any point between 1 and T; E Max represents the maximum capacity of the energy storage battery pack; E 0 represents the initial energy storage battery pack in the selected time period The energy state at any moment, the time period is composed of T time intervals; T represents the total number of selected time intervals;

式(10)表示在所选时间周期内的任一时段储能电池组的能量状态不得为负,也不得超过其能量容量限制;式(11)表示经过一个时间周期,储能电池组的能量状态应保持平衡,即在一个时间周期内储能电池组的充电总量与放电总量应相等;Equation (10) indicates that the energy state of the energy storage battery pack must not be negative at any time within the selected time period, nor exceed its energy capacity limit; Equation (11) indicates that after a time period, the energy storage battery pack The state should be balanced, that is, the total charge and discharge of the energy storage battery pack should be equal within a period of time;

传输线和变压器容量约束:与功率从一个节点流向另一个节点的形式一致,如下式所示:Transmission line and transformer capacity constraints: Consistent with the form of power flow from one node to another, as shown in the following equation:

Figure BDA0003997203750000041
Figure BDA0003997203750000041

式中,Tt表示线路导纳矩阵;式中,

Figure BDA0003997203750000042
和PL分别表示传输线功率的上下限;In the formula, T t represents the line admittance matrix; in the formula,
Figure BDA0003997203750000042
and PL respectively represent the upper and lower limits of the transmission line power;

注意,式(12)中的Tt和式(2)中的Bt都会因观察到当前时间跨度下有线路切换动作而变成时变的;式(2)-式(12)中t表示第t个时间区间;Note that both T t in Equation (12) and B t in Equation (2) become time-varying due to the observation of line switching actions in the current time span; t in Equation (2)-Equation (12) represents the tth time interval;

所建立模型的目标函数是在选定的时间区间内,考虑储能电池组出力,使变压器负载率超阈值时间区间数最小;其中阈值受用电情况影响是时变的,用于反映一天中不同时间区间的能源成本差异;目标函数如式(13)所示;The objective function of the established model is to minimize the number of time intervals in which the transformer load rate exceeds the threshold in the selected time interval, considering the output of the energy storage battery pack; the threshold is time-varying due to the influence of power consumption, and is used to reflect the Energy cost difference in different time intervals; the objective function is shown in formula (13);

Figure BDA0003997203750000043
Figure BDA0003997203750000043

式中,

Figure BDA0003997203750000044
表示变压器负载率是否过载的系数,其中t=p+1,p+2,…,T;φZ表示变压器负载率超阈值总数;
Figure BDA0003997203750000045
表示t时间区间下的变压器负载率阈值;In the formula,
Figure BDA0003997203750000044
The coefficient indicating whether the transformer load rate is overloaded, where t=p+1,p+2,...,T; φ Z indicates the total number of transformer load rates exceeding the threshold;
Figure BDA0003997203750000045
Indicates the transformer load rate threshold under the t time interval;

建立如下整体多时间区间最优潮流模型:The following overall multi-time interval optimal power flow model is established:

Figure BDA0003997203750000046
Figure BDA0003997203750000046

进一步地,整体多时间区间最优潮流模型求解各时间区间储能电池组的功率输出情况,而后基于输出情况给出储能电池组的运行策略;Furthermore, the overall multi-time interval optimal power flow model solves the power output of the energy storage battery group in each time interval, and then gives the operation strategy of the energy storage battery group based on the output situation;

在负荷高峰的时间区间中,接入的储能电池组作为电源放电,为系统输入电能以降低负荷高峰值,在负荷低谷的时间区间中,储能电池则作为负荷的一种,从系统吸收电能从而为后续负荷高峰时间区间的再一次调峰做准备。In the time interval of the peak load, the connected energy storage battery pack is discharged as a power source, and the electric energy is input to the system to reduce the peak load. The electric energy thus prepares for another peak shaving in the subsequent peak load time interval.

进一步地,当有经自回归模型获取的负荷和可再生能源的预测数据时,每个预设的时间间隔求解一次整体多时间区间最优潮流模型,通过增加对储能电池组的调度,实现最佳的调峰效果。Furthermore, when there are load and renewable energy forecast data obtained through the autoregressive model, the overall multi-time interval optimal power flow model is solved once at each preset time interval, and by increasing the scheduling of energy storage battery packs, the realization of The best peaking effect.

进一步地,所述的步骤S3中,构建负荷峰谷差率指标,并以负荷峰谷差率指标对所建立模型的调峰进行负荷波动范围的评估分析;具体如下:Further, in the step S3, the load peak-to-valley difference rate index is constructed, and the load peak-to-valley difference rate index is used to evaluate and analyze the load fluctuation range of the established model; the details are as follows:

负荷峰谷差率:描述一个或多个采样周期内电网负荷的波动范围,其数值越小,表示负荷的波动范围越小;其表达式如下:Load peak-to-valley difference rate: describes the fluctuation range of the grid load within one or more sampling periods, the smaller the value, the smaller the load fluctuation range; its expression is as follows:

Figure BDA0003997203750000047
Figure BDA0003997203750000047

式中,β表示负荷峰谷差率;i表示采样周期数;

Figure BDA0003997203750000051
Figure BDA0003997203750000052
分别表示采样周期内的负荷最大值和最小值。In the formula, β represents the load peak-to-valley difference rate; i represents the number of sampling cycles;
Figure BDA0003997203750000051
and
Figure BDA0003997203750000052
represent the maximum and minimum values of the load in the sampling period, respectively.

本发明具有的有益效果如下:The beneficial effects that the present invention has are as follows:

本发明基于储能电池对缓解变压器过载的作用是双重的这一基本思想,构建了基于多时间区间的最优潮流模型,提出了储能电池参与调峰的运行策略,即在负荷高峰期,接入的储能电池作为电源放电为系统输入合适电能,在负荷低谷时储能电池则作为负荷的一种从系统吸收合适电能,实现了对电网的调峰效果,并且缓解了燃煤机组退役时主变压器和线路过载的压力。Based on the basic idea that the energy storage battery plays a dual role in alleviating the overload of the transformer, the present invention constructs an optimal power flow model based on multiple time intervals, and proposes an operation strategy for the energy storage battery to participate in peak regulation, that is, during the peak load period, The connected energy storage battery is discharged as a power supply to input suitable electric energy for the system, and when the load is low, the energy storage battery is used as a load to absorb appropriate electric energy from the system, realizing the peak-shaving effect on the power grid, and alleviating the decommissioning of coal-fired units When the main transformer and line overload pressure.

附图说明Description of drawings

图1是本发明所面向的一个场景图;Fig. 1 is a scene graph that the present invention faces;

图2是本发明提出的基于多时段最优潮流的储能参与调峰运行策略的流程图;Fig. 2 is a flow chart of the energy storage participating in the peak-shaving operation strategy based on the multi-period optimal power flow proposed by the present invention;

图3是本发明应用例中采用所提储能参与调峰的运行策略前后主变压器功率和储能电池功率及荷电状态的结果图。Fig. 3 is a result diagram of main transformer power, energy storage battery power and state of charge before and after adopting the proposed operation strategy of energy storage participating in peak regulation in the application example of the present invention.

具体实施方式Detailed ways

下面结合附图和具体实施方式对本发明做进一步阐述和说明。The present invention will be further elaborated and illustrated below in conjunction with the accompanying drawings and specific embodiments.

在下面的描述中阐述了很多具体细节以便于充分理解本发明,但是本发明还可以采用其他不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本发明内涵的情况下做类似推广,因此本发明不受下面公开的具体实施例的限制。In the following description, a lot of specific details are set forth in order to fully understand the present invention, but the present invention can also be implemented in other ways different from those described here, and those skilled in the art can do it without departing from the meaning of the present invention. By analogy, the present invention is therefore not limited to the specific examples disclosed below.

在本发明的一个较佳实施例中,根据浙江电网实际典型变电站结构,把附图1所示情况作为测试所提运行策略的场景。根据图1所示的场景:500kV骨干网简称为电源G1,通过连接B1和B2的变压器向220kV网络供电。网状的220kV网络被简称为一个有B3—B4三个总线的环,其中一个燃煤发电机G4将被退役。由潮流图可以看出,发电机能够为局部负载提供电源,从而降低变压器T1的负载状况。然而,当它退役后,220kV电网的所有负载都必须由变压器T1提供,导致B1到B2的潮流明显增加,同时导致T1过载,负荷峰值下T1和线路的压力都将增加。In a preferred embodiment of the present invention, according to the actual typical substation structure of Zhejiang Power Grid, the situation shown in Figure 1 is used as a scenario for testing the proposed operation strategy. According to the scenario shown in Figure 1: the 500kV backbone network is referred to as power supply G1 for short, and supplies power to the 220kV network through the transformer connecting B1 and B2. The meshed 220kV network is simply referred to as a ring with three buses B3-B4, and one of the coal-fired generators, G4, will be decommissioned. It can be seen from the power flow diagram that the generator can provide power for partial loads, thereby reducing the load condition of the transformer T1. However, when it is decommissioned, all the loads of the 220kV grid must be provided by transformer T1, resulting in a significant increase in the power flow from B1 to B2, while causing T1 to be overloaded, and the stress on T1 and the line will increase under load peaks.

为了缓解这种变压器和线路过载情况,分布式发电和需求响应是有效的备选方案。然而,由于这些方案的分布式性质或隐私问题,系统操作员可能无法直接访问这些方案。因此,储能调峰被认为是解决这一问题的理想技术。为了验证使用本发明所提储能电池调峰运行策略能有效缓解已识别的变压器过载,根据实际,即将退役的发电机容量为200MW的燃煤火力发电机,假设在退役发电机原址安装了一个100MW/100MWh的储能电站,这在实践中安装更为便捷,因为设施建设和服务线路可以直接重用。To alleviate this transformer and line overload situation, distributed generation and demand response are effective alternatives. However, system operators may not have direct access to these schemes due to their distributed nature or privacy concerns. Therefore, energy storage peak shaving is considered to be an ideal technology to solve this problem. In order to verify that the peak-shaving operation strategy of the energy storage battery proposed in the present invention can effectively alleviate the identified transformer overload, according to the actual situation, a coal-fired thermal power generator with a generator capacity of 200MW to be decommissioned is assumed to be installed at the original site of the decommissioned generator. 100MW/100MWh energy storage power station, which is more convenient to install in practice, because the facility construction and service lines can be directly reused.

本发明提供了一种基于多时间区间最优潮流和储能电池的电网调峰方法,如图2所示,该方法包括如下步骤:首先需收集一定数量的历史数据,根据线性约束和误差最小目标用来得到自回归模型的p个自回归系数;而后根据自回归模型得到所选时间的预测数据;接着根据多时间区段最优潮流模型迭代计算得到储能电池在各时间区段的具体出力情况,迭代过程中通过比较前后两次结果的负荷峰谷差指标优劣来判断是否迭代结束,最终得到合适的储能电池运行策略。具体步骤如下:The present invention provides a power grid peak regulation method based on multi-time interval optimal power flow and energy storage batteries. As shown in Figure 2, the method includes the following steps: first, a certain amount of historical data needs to be collected, and according to the linear constraints and the minimum error The objective is to obtain the p autoregressive coefficients of the autoregressive model; then obtain the forecast data at the selected time according to the autoregressive model; In terms of output, during the iteration process, it is judged whether the iteration is over by comparing the load peak-valley difference indicators of the two results before and after, and finally an appropriate energy storage battery operation strategy is obtained. Specific steps are as follows:

S1:采用时间序列分析法的自回归模型预测负荷和风力/太阳能的数据。具体为:S1: Load and wind/solar data forecasted by autoregressive models using time series analysis. Specifically:

采用时间序列分析法的自回归模型对区域负荷和风力/太阳能数据进行预测,可用自变量数列来进行预测,其预测原理是用现时的干扰和有限项过去的观测值来预测模型的现时值,将预测值用于建立前瞻性优化形式,自回归模型的数学表示方法为:The autoregressive model of the time series analysis method is used to predict the regional load and wind/solar energy data, and the independent variable series can be used for prediction. The prediction principle is to use the current disturbance and the past observation value of the limited items to predict the current value of the model. Using the predicted values to establish a forward-looking optimization form, the mathematical representation of the autoregressive model is:

Figure BDA0003997203750000061
Figure BDA0003997203750000061

式中,

Figure BDA0003997203750000062
为自回归系数,其中i=1,2,3,…,p;p表示所选历史数据时刻数;k表示需预测的未来时刻,xt为一个时间序列,其中t=p+1,p+2,…T0;εt为一个白噪点;通过一定数量历史数据构建线性方程组结合预测误差最小可得到各自回归系数,假设有n组历史数据{a1,1,a1,2,…,a1,p+1,a2,1,…an,p+1}(n>p),则根据上式可构建如下线性方程组:In the formula,
Figure BDA0003997203750000062
is the autoregressive coefficient, where i=1,2,3,...,p; p represents the number of selected historical data moments; k represents the future time to be predicted, x t is a time series, where t=p+1,p +2,...T 0 ; ε t is a white noise point; through a certain amount of historical data to construct a linear equation system combined with the minimum prediction error, the respective regression coefficients can be obtained, assuming that there are n sets of historical data {a 1,1 ,a 1,2 , …,a 1,p+1 ,a 2,1 ,…a n,p+1 }(n>p), then the following linear equations can be constructed according to the above formula:

Figure BDA0003997203750000063
Figure BDA0003997203750000063

Figure BDA0003997203750000064
Figure BDA0003997203750000064

......

Figure BDA0003997203750000065
Figure BDA0003997203750000065

Figure BDA0003997203750000066
最小为目标,通过求解上述线性方程组即可得到各自回归系数。by
Figure BDA0003997203750000066
The minimum is the goal, and the respective regression coefficients can be obtained by solving the above linear equations.

根据式(1),将一定历史负荷或风力/太阳能数据作为历史数据样本

Figure BDA0003997203750000067
Figure BDA0003997203750000068
于是未来时段预测数据
Figure BDA0003997203750000069
可表示为:According to formula (1), a certain historical load or wind/solar data is taken as a historical data sample
Figure BDA0003997203750000067
Figure BDA0003997203750000068
Therefore, the forecast data for the future period
Figure BDA0003997203750000069
Can be expressed as:

Figure BDA00039972037500000610
Figure BDA00039972037500000610

式中,X表示负荷或风力/太阳能。where X represents load or wind/solar power.

S2:考虑一组前瞻时间区间,基于自回归模型的预测数据,每个时间区间可以建立一个直流潮流,以变压器负载率超阈值数最小为目标函数,建立整体多时间区间最优潮流模型。具体为:考虑一组前瞻时间区间ST={p+1,p+2,…,t,…,T0},每个时间区间t可以建立一个直流潮流,如式(3)所示。S2: Considering a set of forward-looking time intervals, based on the forecast data of the autoregressive model, a DC power flow can be established for each time interval, and the objective function is to establish the overall multi-time interval optimal power flow model with the minimum number of transformer load rates exceeding the threshold. Specifically: consider a set of forward-looking time intervals S T ={p+1,p+2,...,t,...,T 0 }, each time interval t can establish a DC power flow, as shown in formula (3).

Figure BDA00039972037500000611
Figure BDA00039972037500000611

式中,AG和AESS分别表示发电机和储能电池组的连接矩阵;

Figure BDA00039972037500000612
Figure BDA00039972037500000613
分别表示时间区间t下发电机、储能电池组和负载的功率;Bt和θt分别表示系统的导纳矩阵和节点电压相角在时间区间t下的虚部。In the formula, A G and A ESS respectively represent the connection matrix of the generator and the energy storage battery pack;
Figure BDA00039972037500000612
and
Figure BDA00039972037500000613
Respectively represent the power of generator, energy storage battery pack and load in the time interval t; B t and θ t represent the admittance matrix of the system and the imaginary part of the node voltage phase angle in the time interval t, respectively.

首先,利用一组变量Et对储能电池组的荷电状态(SOC)进行跟踪。它与储能电池充放电功率的联系如式(4)所示。First, a set of variables E t is used to track the state of charge (SOC) of the energy storage battery pack. The relationship between it and the charging and discharging power of the energy storage battery is shown in formula (4).

Figure BDA0003997203750000071
Figure BDA0003997203750000071

式中,

Figure BDA0003997203750000072
表示t时刻储能电池的充放电功率。In the formula,
Figure BDA0003997203750000072
Indicates the charging and discharging power of the energy storage battery at time t.

对于所选系统,功率平衡约束是最重要的约束之一,如式(5)所示。For the selected system, the power balance constraint is one of the most important constraints, as shown in Equation (5).

Figure BDA0003997203750000073
Figure BDA0003997203750000073

式中,Ng表示燃煤机组的数量;

Figure BDA0003997203750000074
Figure BDA0003997203750000075
分别表示t时刻的风力/太阳能出力和波动量;
Figure BDA0003997203750000076
表示t时刻的线损功率;
Figure BDA0003997203750000077
表示t时刻在j位置的负荷功率。In the formula, Ng represents the number of coal-fired units;
Figure BDA0003997203750000074
and
Figure BDA0003997203750000075
Respectively represent the wind/solar output and fluctuations at time t;
Figure BDA0003997203750000076
Indicates the line loss power at time t;
Figure BDA0003997203750000077
Indicates the load power at position j at time t.

发电机的机组出力约束如下:The unit output constraints of the generator are as follows:

Figure BDA0003997203750000078
Figure BDA0003997203750000078

式中,

Figure BDA0003997203750000079
和PG分别表示发电机出力的上下限,特别的,当发电机离线时上下限都应取0。In the formula,
Figure BDA0003997203750000079
and PG respectively represent the upper and lower limits of the generator output, especially, when the generator is offline, both the upper and lower limits should be set to 0.

此外,对发电机考虑了爬坡约束,如式(7)所示。但对储能电池组则不考虑,因为储能电池组在以分钟为单位的运行时间间隔下,具有充分的充放电调整率。In addition, the ramp constraint is considered for the generator, as shown in Equation (7). However, it is not considered for the energy storage battery pack, because the energy storage battery pack has a sufficient charge and discharge adjustment rate under the operating time interval in minutes.

Figure BDA00039972037500000710
Figure BDA00039972037500000710

式中,RG

Figure BDA00039972037500000711
分别表示发电机爬坡的下限和上限。In the formula, R G and
Figure BDA00039972037500000711
Respectively represent the lower limit and upper limit of generator ramp.

电池储能运行约束:Battery energy storage operating constraints:

Figure BDA00039972037500000712
Figure BDA00039972037500000712

Figure BDA00039972037500000713
Figure BDA00039972037500000713

Figure BDA00039972037500000714
Figure BDA00039972037500000714

式中,

Figure BDA00039972037500000715
Figure BDA00039972037500000716
分别表示t时刻处电池储能电站的放电和充电功率;
Figure BDA00039972037500000717
Figure BDA00039972037500000718
分别表示储能电池的额定放电和充电功率;
Figure BDA00039972037500000719
Figure BDA00039972037500000720
分别表示t时刻处电池储能电站的放电和充电状态,且皆为0-1变量,可根据实际考虑的时间区间内储能电池的具体状态确定这两个参数的值:充电状态时
Figure BDA00039972037500000721
取1,
Figure BDA00039972037500000722
取0;放电状态时
Figure BDA00039972037500000723
取0,
Figure BDA00039972037500000724
取1;特别的,若储能电池为离线状态,则两个参数皆设为0。In the formula,
Figure BDA00039972037500000715
and
Figure BDA00039972037500000716
respectively represent the discharge and charge power of the battery energy storage power station at time t;
Figure BDA00039972037500000717
and
Figure BDA00039972037500000718
respectively represent the rated discharge and charge power of the energy storage battery;
Figure BDA00039972037500000719
and
Figure BDA00039972037500000720
represent the discharge and charge states of the battery energy storage power station at time t, respectively, and both are 0-1 variables. The values of these two parameters can be determined according to the specific state of the energy storage battery in the actually considered time interval:
Figure BDA00039972037500000721
take 1,
Figure BDA00039972037500000722
Take 0; in discharge state
Figure BDA00039972037500000723
take 0,
Figure BDA00039972037500000724
Take 1; in particular, if the energy storage battery is offline, both parameters are set to 0.

此外,储能电池的能量状态约束如下:In addition, the energy state constraints of the energy storage battery are as follows:

Figure BDA0003997203750000081
Figure BDA0003997203750000081

Figure BDA0003997203750000082
Figure BDA0003997203750000082

式中,

Figure BDA0003997203750000083
Figure BDA0003997203750000084
分别表示储能电池的充电效率和放电效率;EMax表示储能电池的最大容量;E0表示储能电池在所选时间周期中初始时刻的能量状态;T表示所选时间区间总数。τ表示1到T之间的任意一个点;时间周期由T个时间区间构成In the formula,
Figure BDA0003997203750000083
and
Figure BDA0003997203750000084
Respectively represent the charging efficiency and discharge efficiency of the energy storage battery; E Max represents the maximum capacity of the energy storage battery; E 0 represents the energy state of the energy storage battery at the initial moment in the selected time period; T represents the total number of selected time intervals. τ represents any point between 1 and T; the time period consists of T time intervals

式(11)表示在所选时间周期内的任一时段储能电池的能量状态不得为负,也不得超过其能量容量限制;式(12)表示经过一个时间周期,储能电池的能量状态应保持平衡,即在一个时间周期内储能电池的充电总量与放电总量应相等。Equation (11) indicates that the energy state of the energy storage battery must not be negative at any time within the selected time period, nor exceed its energy capacity limit; Equation (12) indicates that after a time period, the energy state of the energy storage battery should be Maintain balance, that is, the total charge and discharge of the energy storage battery should be equal within a period of time.

传输线和变压器容量约束情况与功率从一个节点流向另一个节点的形式一致,如式(13)所示。The transmission line and transformer capacity constraints are consistent with the form of power flow from one node to another, as shown in Equation (13).

Figure BDA0003997203750000085
Figure BDA0003997203750000085

式中,Tt表示线路导纳矩阵,

Figure BDA0003997203750000086
和PL分别表示传输线功率的上下限。注意Tt和Bt都会因观察到当前时间跨度下有线路切换动作而变成时变的。where T t represents the line admittance matrix,
Figure BDA0003997203750000086
and PL represent the upper and lower limits of the transmission line power, respectively. Note that both T t and B t will become time-varying due to the observed line switching action in the current time span.

式(3)-式(13)中的t都表示第t个时间区间。The t in formula (3) - formula (13) all represent the tth time interval.

所建立模型的目标函数是在选定的时间区间内,考虑储能电池的出力情况,使变压器负载率超阈值数最小化。其中阈值受用电情况影响是时变的,可反映一天中不同时间区间的能源成本差异。目标函数如式(14)所示。The objective function of the established model is to minimize the number of transformer load rates exceeding the threshold within the selected time interval, considering the output of the energy storage battery. The threshold value is time-varying due to the influence of power consumption, which can reflect the energy cost difference in different time intervals of the day. The objective function is shown in formula (14).

Figure BDA0003997203750000087
Figure BDA0003997203750000087

式中,

Figure BDA0003997203750000088
表示变压器负载率是否过载的系数,其中t=p+1,p+2,…,T;φZ表示变压器负载率超阈值总数;
Figure BDA0003997203750000089
表示t时间区间下的变压器负载率阈值。In the formula,
Figure BDA0003997203750000088
The coefficient indicating whether the transformer load rate is overloaded, where t=p+1,p+2,...,T; φ Z indicates the total number of transformer load rates exceeding the threshold;
Figure BDA0003997203750000089
Indicates the transformer load rate threshold in the t time interval.

综上,可以建立如下整体多时间区间最优潮流模型:In summary, the following overall multi-time interval optimal power flow model can be established:

Figure BDA00039972037500000810
Figure BDA00039972037500000810

当有经自回归模型获取的负荷和可再生能源的预测数据时,每隔一个时间间隔即15分钟求解一次所建立的模型(15)。因此,通过增加对储能电池组的调度,可实现最佳的调峰效果,同时满足各种约束条件,包括缓解变压器的过载压力。When there are load and renewable energy forecast data obtained through the autoregressive model, the established model (15) is solved every 15 minutes. Therefore, by increasing the scheduling of energy storage battery packs, the best peak shaving effect can be achieved while satisfying various constraints, including alleviating the overload pressure of the transformer.

S3:求解所建立的整体多时间区间最优潮流模型,提出储能电池参与调峰的运行策略,并以负荷峰谷差率为指标对该模型的调峰效果进行评估分析。S3: Solve the established overall multi-time interval optimal power flow model, propose an operation strategy for energy storage batteries to participate in peak regulation, and evaluate and analyze the peak regulation effect of the model with the load peak-to-valley difference rate index.

在根据上述所提整体多时间区间最优潮流模型求解得到各时段储能电池组的功率输出情况后,可基于此提出负荷高峰期的储能电池运行策略,即在负荷高峰的时间区间中,接入的储能电池作为电源放电为系统输入合适电能以降低负荷高峰值,在负荷低谷的时间区间中,储能电池则作为负荷的一种从系统吸收合适电能从而为后续负荷高峰时间区间的再一次调峰做准备。After obtaining the power output of the energy storage battery pack at each time period based on the above-mentioned overall multi-time interval optimal power flow model, the operation strategy of the energy storage battery during the peak load period can be proposed based on this, that is, in the time interval of the peak load, The connected energy storage battery is used as a power supply to discharge the appropriate electric energy for the system to reduce the peak load. In the time interval of the low load, the energy storage battery is used as a load to absorb the appropriate electric energy from the system to provide for the subsequent load peak time interval. Prepare for peak shaving again.

为评估分析所提模型的调峰效果,构建负荷峰谷差率指标。具体如下:In order to evaluate and analyze the peak-shaving effect of the proposed model, a load peak-to-valley difference rate index is constructed. details as follows:

负荷峰谷差率:描述一个或多个采样周期内电网负荷的波动范围,其数值越小,表示负荷的波动范围越小。其表达式如下:Load peak-to-valley difference rate: describes the fluctuation range of the grid load within one or more sampling periods, the smaller the value, the smaller the load fluctuation range. Its expression is as follows:

Figure BDA0003997203750000091
Figure BDA0003997203750000091

式中,β表示负荷峰谷差率;i表示采样周期数;

Figure BDA0003997203750000092
Figure BDA0003997203750000093
分别表示采样周期内的负荷最大值和最小值。In the formula, β represents the load peak-to-valley difference rate; i represents the number of sampling cycles;
Figure BDA0003997203750000092
and
Figure BDA0003997203750000093
represent the maximum and minimum values of the load in the sampling period, respectively.

附图3为典型夏季高峰日的变压器加载情况及储能充放电运行情况,时间间隔为15分钟。可以观察到储能电池能够通过在非负荷高峰时充电,并在负荷高峰释放能量来缓解变压器的过载,成功实现调峰目的。迭代过程中通过负荷峰谷差指标的比较,可保证所提策略的调峰效果。同时,从中可发现,本策略对于储能电站的容量要求较为灵活。当储能电站容量较小时,可选择负荷非峰值对储能电站适当充电,而后在适当的时间放电即可起到缓解变压器过载和调峰的目的;当储能电站容量较大时,在非负荷高峰期可充入更多的能量,进而通过本策略可实现更好的调峰目的。Attached Figure 3 shows the transformer loading and energy storage charging and discharging operation on a typical summer peak day, with a time interval of 15 minutes. It can be observed that the energy storage battery can relieve the overload of the transformer by charging at non-load peak hours and releasing energy at load peak hours, and successfully achieve the purpose of peak regulation. In the iterative process, the peak-shaving effect of the proposed strategy can be guaranteed by comparing the load peak-to-valley difference index. At the same time, it can be found that this strategy has more flexible requirements for the capacity of energy storage power stations. When the capacity of the energy storage power station is small, you can choose the off-peak load to properly charge the energy storage power station, and then discharge it at an appropriate time to alleviate the transformer overload and peak regulation; when the capacity of the energy storage power station is large, in non-peak More energy can be charged during the peak load period, and better peak shaving can be achieved through this strategy.

以上所述仅为本说明书一个或多个实施例的较佳实施例而已,并不用以限制本说明书一个或多个实施例,凡在本说明书一个或多个实施例的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本说明书一个或多个实施例保护的范围之内。The above descriptions are only preferred embodiments of one or more embodiments of this specification, and are not intended to limit one or more embodiments of this specification. Within the spirit and principles of one or more embodiments of this specification, Any modification, equivalent replacement, improvement, etc. should be included in the scope of protection of one or more embodiments of this specification.

Claims (6)

1. A power grid peak shaving method based on multi-time interval optimal power flow and an energy storage battery is characterized by comprising the following steps:
s1: predicting load and wind/solar data by using an autoregressive model of a time series analysis method;
s2: obtaining a group of forward looking time intervals based on control requirements, establishing a direct current power flow for each time interval based on prediction data of an autoregressive model, considering the climbing constraint and the power generation constraint of a generator, combining the charge state constraint and the power constraint of energy storage and the capacity constraint of a transmission line and a transformer, synthesizing the output of the generator and an energy storage battery, and establishing an integral multi-time interval optimal power flow model by taking the minimum number of time intervals when the load rate of the transformer exceeds a threshold as a target function;
s3: and solving the established integral multi-time interval optimal power flow model to obtain the power output condition of the energy storage battery pack at each time interval, thereby obtaining an operation strategy that the energy storage battery participates in peak shaving, and evaluating and analyzing the peak shaving effect of the load fluctuation range of the model by taking the load peak-valley difference rate as an index.
2. The method for peak load regulation of a power grid based on an optimal power flow and an energy storage battery in multiple time intervals as claimed in claim 1, wherein the step S1 specifically comprises: predicting a current value of the model by using current interference and a limited past observation value, and using the predicted value to establish a prospective optimization form;
using historical load or wind/solar data as historical data samples
Figure FDA0003997203740000011
In the futurePredicting data
Figure FDA0003997203740000012
Expressed as:
Figure FDA0003997203740000013
in the formula (I), the compound is shown in the specification,
Figure FDA0003997203740000014
is an autoregressive coefficient, where i =0,1,2,3, …, p, p represents the selected historical data time instant; k represents the future time to be predicted; the autoregressive coefficient is obtained by constructing a linear equation set through historical data and combining the minimum prediction error, X represents load or wind power/solar energy, and epsilon t Is a white noise point.
3. The method for peak load regulation of a power grid based on the optimal power flow and the energy storage battery in multiple time intervals as claimed in claim 2, wherein the step S2 specifically comprises: consider a set of look-ahead time intervals S T ={p+1,p+2,…,T 0 And creating a direct current flow in each time interval t, as shown in formula (2):
Figure FDA0003997203740000015
in the formula, A G And A ESS Respectively representing the connection matrixes of the generator and the energy storage battery pack;
Figure FDA0003997203740000016
and
Figure FDA0003997203740000017
respectively representing the power of the generator, the energy storage battery pack and the load in a time interval t; b is t And theta t Respectively representing the imaginary parts of the admittance matrix and the node voltage phase angle of the system in a time interval t;
firstly, tracking the charge state of an energy storage battery pack by using a group of variables; variable E t Charging and discharging power of energy storage battery
The relation of (A) is shown as a formula (3);
Figure FDA0003997203740000021
the power balance constraint of the system is shown as equation (4);
Figure FDA0003997203740000022
wherein Ng represents the number of generators;
Figure FDA0003997203740000023
representing the power of the generator i in a time interval t;
Figure FDA0003997203740000024
and
Figure FDA0003997203740000025
respectively representing wind power/solar power output and fluctuation quantity in a time interval t;
Figure FDA0003997203740000026
representing the line loss power in a time interval t;
Figure FDA0003997203740000027
representing the load power at position j for the time interval t,
Figure FDA0003997203740000028
respectively representing the discharging power and the charging power of the energy storage battery pack at the position j in the time interval t;
the unit output of the generator is constrained as follows:
Figure FDA0003997203740000029
in the formula (I), the compound is shown in the specification,
Figure FDA00039972037400000210
and P G Respectively representing the upper limit and the lower limit of the output of the generator;
the generator is considered to be climbing constrained, as shown in equation (6):
Figure FDA00039972037400000211
in the formula, R G And
Figure FDA00039972037400000212
respectively representing the lower limit and the upper limit of the generator climbing slope;
the power constraints of the energy storage battery pack comprise energy storage battery operation constraints and energy state constraints, wherein the operation constraints are represented by the following formula:
Figure FDA00039972037400000213
Figure FDA00039972037400000214
Figure FDA00039972037400000215
in the formula (I), the compound is shown in the specification,
Figure FDA00039972037400000216
and
Figure FDA00039972037400000217
respectively representing the discharging power and the charging power of the energy storage battery pack under the time interval t;
Figure FDA00039972037400000218
and
Figure FDA00039972037400000219
respectively representing rated discharge and charge power of the energy storage battery pack;
Figure FDA00039972037400000220
and
Figure FDA00039972037400000221
respectively representing the discharging state and the charging state of the energy storage battery pack in a time interval t, wherein the discharging state and the charging state are all variables of 0-1, and determining the values of the two parameters according to the specific state of the generator/the energy storage battery in the actually considered time interval;
the energy constraint is shown as follows;
Figure FDA00039972037400000222
Figure FDA0003997203740000031
in the formula (I), the compound is shown in the specification,
Figure FDA0003997203740000032
and
Figure FDA0003997203740000033
respectively representing the charging efficiency and the discharging efficiency of the energy storage battery pack; τ represents any one point between 1 and T; e Max Representing the maximum capacity of the energy storage battery pack; e 0 Representing the energy state of the energy storage battery pack at the initial moment in a selected time period, wherein the time period consists of T time intervals; t represents a selected time zoneThe total number of cells;
equation (10) indicates that the energy state of the energy storage battery pack must not be negative nor exceed its energy capacity limit at any time during the selected time period; equation (11) shows that the energy states of the energy storage battery pack should be balanced after a time period, that is, the total charge and the total discharge of the energy storage battery pack should be equal in a time period;
transmission line and transformer capacity constraints: consistent with the form of power flowing from one node to another, the following equation applies:
Figure FDA0003997203740000034
in the formula, T t Representing a line admittance matrix; in the formula (I), the compound is shown in the specification,
Figure FDA0003997203740000035
and P L Respectively representing the upper limit and the lower limit of the transmission line power;
note that T in the formula (12) t And B in the formula (2) t Will become time-varying due to the observation of the line switching action at the current time span; formula (2) -formula (12) wherein t represents the t-th time interval;
the objective function of the established model is that the output of the energy storage battery pack is considered in a selected time interval, so that the number of time intervals when the load rate of the transformer exceeds a threshold value is minimum; the threshold value is influenced by the power utilization condition and is time-varying, and is used for reflecting the energy cost difference of different time intervals in one day; the objective function is shown in equation (13);
Figure FDA0003997203740000036
in the formula (I), the compound is shown in the specification,
Figure FDA0003997203740000037
a coefficient representing whether the transformer load factor is overloaded or not, where T = p +1, p +2, …, T; phi is a Z Representing a voltage transformationTotal number of machine load rate exceeding threshold;
Figure FDA0003997203740000038
representing a transformer load rate threshold value in a time interval t;
establishing an overall multi-time interval optimal power flow model as follows:
Figure FDA0003997203740000039
4. the power grid peak shaving method based on the multi-time interval optimal power flow and the energy storage battery as claimed in claim 3, characterized in that the overall multi-time interval optimal power flow model solves the power output condition of the energy storage battery pack in each time interval, and then gives the operation strategy of the energy storage battery pack based on the output condition;
in the time interval of the load peak, the accessed energy storage battery pack is discharged as a power supply to input electric energy for the system so as to reduce the load peak value, and in the time interval of the load valley, the energy storage battery is used as one type of load to absorb the electric energy from the system so as to prepare for the next peak regulation in the subsequent load peak time interval.
5. The power grid peak regulation method based on the optimal power flow in multiple time intervals and the energy storage battery as claimed in claim 1, wherein when prediction data of load and renewable energy sources are obtained through an autoregressive model, the optimal power flow model in multiple time intervals is solved once every preset time interval, and the optimal peak regulation effect is achieved by increasing the dispatching on the energy storage battery pack.
6. The method for peak shaving of power grid based on optimal power flow and energy storage battery in multiple time intervals as claimed in claim 1, wherein in the step S3, a load peak-to-valley difference rate index is constructed, and the peak shaving of the established model is subjected to estimation analysis of load fluctuation range by using the load peak-to-valley difference rate index; the method comprises the following specific steps:
load peak-to-valley difference rate: describing the fluctuation range of the power grid load in one or more sampling periods, wherein the smaller the numerical value of the fluctuation range, the smaller the fluctuation range of the load is; the expression is as follows:
Figure FDA0003997203740000041
in the formula, beta represents a load peak-valley difference rate; i represents the number of sampling cycles;
Figure FDA0003997203740000042
and
Figure FDA0003997203740000043
representing the load maximum and minimum values within the sampling period, respectively.
CN202211600444.XA 2022-12-13 2022-12-13 A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery Pending CN115833203A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211600444.XA CN115833203A (en) 2022-12-13 2022-12-13 A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211600444.XA CN115833203A (en) 2022-12-13 2022-12-13 A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery

Publications (1)

Publication Number Publication Date
CN115833203A true CN115833203A (en) 2023-03-21

Family

ID=85547039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211600444.XA Pending CN115833203A (en) 2022-12-13 2022-12-13 A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery

Country Status (1)

Country Link
CN (1) CN115833203A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117175666A (en) * 2023-11-03 2023-12-05 深圳航天科创泛在电气有限公司 A load adjustment method and adjustment device for a distributed energy storage power supply system
CN118889497A (en) * 2024-07-15 2024-11-01 上海勘测设计研究院有限公司 A method and device for controlling an energy storage system applied to a substation
CN119313109A (en) * 2024-12-16 2025-01-14 国网江西省电力有限公司经济技术研究院 A multi-time scale energy storage configuration method and system for eliminating peak loads

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106712075A (en) * 2016-04-26 2017-05-24 武汉大学 Peaking strategy optimization method considering safety constraints of wind power integration system
CN109742796A (en) * 2019-01-10 2019-05-10 华北电力大学 A kind of Multiple Time Scales coordinated scheduling method of scene extreme misery storage association system
CN110601179A (en) * 2019-08-16 2019-12-20 南京理工大学 Receiving-end power grid consumption optimization method for wind power participating in frequency modulation
CN111244993A (en) * 2020-01-21 2020-06-05 国网湖南省电力有限公司 A capacity optimization configuration method for energy storage to participate in grid peak regulation application
WO2021143075A1 (en) * 2020-01-17 2021-07-22 南京东博智慧能源研究院有限公司 Demand response method taking space-time distribution of electric vehicle charging loads into consideration

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106712075A (en) * 2016-04-26 2017-05-24 武汉大学 Peaking strategy optimization method considering safety constraints of wind power integration system
CN109742796A (en) * 2019-01-10 2019-05-10 华北电力大学 A kind of Multiple Time Scales coordinated scheduling method of scene extreme misery storage association system
CN110601179A (en) * 2019-08-16 2019-12-20 南京理工大学 Receiving-end power grid consumption optimization method for wind power participating in frequency modulation
WO2021143075A1 (en) * 2020-01-17 2021-07-22 南京东博智慧能源研究院有限公司 Demand response method taking space-time distribution of electric vehicle charging loads into consideration
CN111244993A (en) * 2020-01-21 2020-06-05 国网湖南省电力有限公司 A capacity optimization configuration method for energy storage to participate in grid peak regulation application

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117175666A (en) * 2023-11-03 2023-12-05 深圳航天科创泛在电气有限公司 A load adjustment method and adjustment device for a distributed energy storage power supply system
CN117175666B (en) * 2023-11-03 2024-01-26 深圳航天科创泛在电气有限公司 A load adjustment method and adjustment device for a distributed energy storage power supply system
CN118889497A (en) * 2024-07-15 2024-11-01 上海勘测设计研究院有限公司 A method and device for controlling an energy storage system applied to a substation
CN118889497B (en) * 2024-07-15 2025-02-14 上海勘测设计研究院有限公司 Energy storage system control method and device applied to transformer area
CN119313109A (en) * 2024-12-16 2025-01-14 国网江西省电力有限公司经济技术研究院 A multi-time scale energy storage configuration method and system for eliminating peak loads
CN119313109B (en) * 2024-12-16 2025-06-13 国网江西省电力有限公司经济技术研究院 A multi-time scale energy storage configuration method and system for eliminating peak loads

Similar Documents

Publication Publication Date Title
Yan et al. A cost accounting method of the Li-ion battery energy storage system for frequency regulation considering the effect of life degradation
Pourmousavi et al. Real-time energy management of a stand-alone hybrid wind-microturbine energy system using particle swarm optimization
CN105207259B (en) Micro-grid system dispatching method under based on energy management and net state
CN110690702B (en) An optimal scheduling and operation method of active distribution network considering comprehensive carrying capacity
CN115833203A (en) A grid peak regulation method based on multi-time interval optimal power flow and energy storage battery
CN105139147A (en) Economic scheduling method for micro-grid system
CN116565908A (en) A flexible traction substation energy management method connected to photovoltaic and energy storage systems
Wang et al. Optimal control of a grid-connected hybrid electrical energy storage system for homes
CN114123280B (en) Battery energy storage power station energy management method considering system efficiency
CN110034611A (en) A kind of peak load shifting mixed energy storage system
CN118074225A (en) A method and system for optimizing the coordinated dispatching of power system sources, grids, loads and storage
CN117856315B (en) Scheduling method and scheduling device of energy storage system
CN110350589A (en) A kind of renewable energy and energy storage scheduling model and dispatching method
Wang et al. A hierarchical control algorithm for managing electrical energy storage systems in homes equipped with PV power generation
CN110276487B (en) Reactive auxiliary service transaction mechanism in virtual power plant environment
CN114243675B (en) Active distribution network optimization method and system considering energy storage system and reactive power compensation
CN116706969A (en) Interactive control method for flexible power distribution system with multiple microgrids based on intelligent soft switch
CN121124129A (en) Methods, systems, equipment and media for assessing the carrying capacity of distributed photovoltaic power generation in distribution networks
CN105405072A (en) Island heuristic load reduction model construction method for active power distribution network
CN112039057B (en) A low-voltage governance method based on two-stage scheduling
CN119813374A (en) A method and system for optimizing energy dispatching of a flexible power grid
CN110224397A (en) It is a kind of scene access background under user side battery energy storage cost effectiveness analysis method
Delavaripour et al. Optimum battery size selection in standalone renewable energy systems
CN113555929B (en) Retired battery energy storage system considering risks and optimal scheduling method thereof
Wang et al. Optimal Configuration of Energy Storage in Distribution Networks Based on Full Life Levelized Cost of Electricity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination