CN111737791A - Prefabricated steel structure building pipeline layout method - Google Patents

Prefabricated steel structure building pipeline layout method Download PDF

Info

Publication number
CN111737791A
CN111737791A CN202010400475.5A CN202010400475A CN111737791A CN 111737791 A CN111737791 A CN 111737791A CN 202010400475 A CN202010400475 A CN 202010400475A CN 111737791 A CN111737791 A CN 111737791A
Authority
CN
China
Prior art keywords
pipeline
building
wall
steel structure
drawings
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010400475.5A
Other languages
Chinese (zh)
Inventor
戴立先
张耀林
周瑜
许航
朱德桥
李萧
孙一
朱湃
严小霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science And Industry Co ltd
Original Assignee
China Construction Science And Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Science And Industry Co ltd filed Critical China Construction Science And Industry Co ltd
Priority to CN202010400475.5A priority Critical patent/CN111737791A/en
Publication of CN111737791A publication Critical patent/CN111737791A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/18Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/16Cables, cable trees or wire harnesses

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Evolutionary Computation (AREA)
  • Computational Mathematics (AREA)
  • Civil Engineering (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Business, Economics & Management (AREA)
  • Structural Engineering (AREA)
  • Economics (AREA)
  • Mechanical Engineering (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种装配式钢结构建筑管线布置方法,所述方法包括如下步骤:获取建筑结构图和管线走向剖面图。获取建筑结构图和管线走向剖面图对应的初始三维模型图。在所述初始三维模型图中,获取在钢梁和/或基墙中的管线走线需要优化的区域。在选取的区域中,根据优化规则对管线排布和/或基墙的位置进行调整优化。根据优化后的三维模型图,输出施工图纸。通过三维建模方式,将管线走线在三维模型图中进行系统设计优化,从而将问题拦截在设计阶段,以提升建筑质量和效率。

Figure 202010400475

The invention discloses a method for arranging pipelines in a prefabricated steel structure building. The method includes the following steps: acquiring a building structure diagram and a pipeline sectional drawing. Obtain the initial 3D model diagram corresponding to the building structure diagram and the pipeline route section diagram. In the initial three-dimensional model drawing, the areas in the steel beams and/or foundation walls that need to be optimized are obtained. In the selected area, the pipeline arrangement and/or the position of the foundation wall are adjusted and optimized according to the optimization rules. According to the optimized 3D model drawings, output construction drawings. Through the 3D modeling method, the pipeline routing is carried out in the 3D model diagram for system design optimization, so as to intercept the problem in the design stage, so as to improve the construction quality and efficiency.

Figure 202010400475

Description

装配式钢结构建筑管线布置方法Prefabricated steel structure building pipeline layout method

技术领域technical field

本发明涉及建筑布置技术领域,特别是涉及一种装配式钢结构建筑管线布置方法。The invention relates to the technical field of building layout, in particular to a pipeline layout method for a prefabricated steel structure building.

背景技术Background technique

现有建筑的管线布置大多是在平面图纸上根据设备以及用电需求,进行管线的平面排布,并根据平面规划的图纸进行施工。然而,通过这种方式进行管线的排布,容易出现管线布置不合理,从而需要进行多次重新规划后再施工,极大的影响效率。而现有的装配式钢结构建筑,以钢框架为支撑,对管线走向的系统性要求更高。在施工过程中,管线走向的不合理甚至会影响建筑的安全性。Most of the pipeline layout of existing buildings is based on the equipment and electricity demand on the plane drawings, the plane layout of pipelines is carried out, and the construction is carried out according to the drawings of the plane plan. However, by arranging pipelines in this way, it is easy to cause unreasonable pipeline layouts, which requires multiple re-planning before construction, which greatly affects the efficiency. The existing prefabricated steel structure buildings, supported by steel frames, have higher systematic requirements for the direction of pipelines. During the construction process, the unreasonable direction of the pipeline may even affect the safety of the building.

发明内容SUMMARY OF THE INVENTION

本发明旨在至少解决现有技术中存在的技术问题之一。为此,本发明提供一种装配式钢结构建筑管线布置方法,通过数字信息仿真模拟建筑物,并在设计阶段对管线排布进行系统设计优化,以提升项目的生产效率和建筑质量。The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention provides a method for arranging pipelines in a prefabricated steel structure building, which simulates buildings through digital information, and systematically optimizes the pipeline layout in the design stage, so as to improve the production efficiency and construction quality of the project.

所述装配式钢结构建筑管线布置方法包括如下步骤:The method for arranging pipelines in an assembled steel structure building includes the following steps:

获取建筑结构图和管线走向剖面图。Obtain building structural drawings and pipeline routing profiles.

获取建筑结构图和管线走向剖面图对应的初始三维模型图。Obtain the initial 3D model diagram corresponding to the building structure diagram and the pipeline route section diagram.

在所述初始三维模型图中,获取在钢梁和/或基墙中的管线走线需要优化的区域。In the initial three-dimensional model drawing, the areas in the steel beams and/or foundation walls that need to be optimized are obtained.

在选取的区域中,根据优化规则对管线排布和/或基墙的位置进行调整优化。In the selected area, the pipeline arrangement and/or the position of the foundation wall are adjusted and optimized according to the optimization rules.

根据优化后的三维模型图,输出施工图纸。According to the optimized 3D model drawings, output construction drawings.

根据本发明的上述实施例,至少具有如下有益效果:通过三维建模方式将建筑信息更加直观的展示,并根据以建筑结构的特征设定的管线走线规则,进行系统设计优化。此时,根据优化后的图纸施工,可以避免由于走线不合理导致返工的现象,以提升建筑的效率和质量。According to the above-mentioned embodiments of the present invention, at least the following beneficial effects are obtained: the building information is displayed more intuitively by means of three-dimensional modeling, and the system design is optimized according to the pipeline routing rules set according to the characteristics of the building structure. At this time, the construction according to the optimized drawings can avoid the phenomenon of rework caused by unreasonable wiring, so as to improve the efficiency and quality of the building.

根据本发明的一些实施例,所述优化规则还包括:所述基墙仅有一侧墙体设置有管线走线。通过仅在墙体一侧设置管线,可以避免由于墙体双面开槽的情况,从而影响墙体的稳定性。According to some embodiments of the present invention, the optimization rule further includes: only one side of the base wall is provided with pipelines. By arranging pipelines only on one side of the wall, it is possible to avoid the situation that the wall is slotted on both sides, thereby affecting the stability of the wall.

根据本发明的一些实施例,所述优化规则包括:所述基墙的位置相对于所述钢梁位置向外凸出;管线垂直于地面,且并向上穿过所述基墙延伸至所述钢梁外侧。通过将基墙的位置外凸于钢梁,可以在钢梁结构无需开槽的情况下,管线可以垂直于地面向上固定在钢梁一侧。既满足管线垂直向上排布,又保证了建筑的安全性。According to some embodiments of the present invention, the optimization rule includes: the position of the foundation wall protrudes outward relative to the position of the steel beam; the pipeline is perpendicular to the ground and extends upward through the foundation wall to the Outside the steel beam. By projecting the position of the base wall to the steel beam, the pipeline can be fixed on one side of the steel beam perpendicular to the ground without the need for grooves in the steel beam structure. It not only satisfies the vertical upward arrangement of pipelines, but also ensures the safety of the building.

根据本发明的一些实施例,所述基墙的位置向外凸出的距离为10-20mm。当设置向外凸出的距离为10-20mm时,管线垂直于地面并向上走线时,基墙不会凸出钢梁过多,从而影响整体外观。According to some embodiments of the present invention, the position of the base wall protrudes outward by a distance of 10-20 mm. When the outwardly protruding distance is set to 10-20mm, when the pipeline is perpendicular to the ground and runs upwards, the base wall will not protrude too much from the steel beam, thus affecting the overall appearance.

根据本发明的一些实施例,装配式钢结构建筑管线走线方法还包括如下步骤:根据施工图纸进行现场施工。通过严格按照设计好的图纸施工,可以提升建筑的效率。According to some embodiments of the present invention, the method for routing the pipelines of the prefabricated steel structure building further includes the following steps: performing on-site construction according to the construction drawings. By strictly following the designed drawings, the efficiency of the building can be improved.

根据本发明的一些实施例,根据施工图纸进行现场施工还包括如下步骤:According to some embodiments of the present invention, the on-site construction according to the construction drawings further includes the following steps:

根据施工图纸,在所述基墙内开槽放置线管。According to the construction drawings, grooves are placed in the base wall to place conduits.

对所述钢梁进行填充,并进行抹灰找平。The steel beams are filled and leveled by plastering.

通过在管线线管排布完成后,将钢梁进行填充和抹灰找平,可以使得线管固定在钢梁一侧,且墙体和钢梁整体更加平整、美观。By filling, plastering and leveling the steel beam after the line and pipe arrangement is completed, the line pipe can be fixed on one side of the steel beam, and the wall and the steel beam as a whole are more flat and beautiful.

根据本发明的一些实施例,所述基墙包括ALC条板。通过ALC搭建基墙的墙体,可以提升建筑的效率。According to some embodiments of the present invention, the base wall comprises ALC slats. Building the base wall through ALC can improve the efficiency of the building.

根据本发明的一些实施例,所述优化后的三维模型图通过BIM软件获取。通过BIM,可以简化三维建筑模型中管线走线的优化过程。According to some embodiments of the present invention, the optimized three-dimensional model diagram is obtained through BIM software. Through BIM, the optimization process of pipeline routing in 3D building models can be simplified.

本发明的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the present invention will be set forth, in part, from the following description, and in part will be apparent from the following description, or may be learned by practice of the invention.

附图说明Description of drawings

本发明的上述和/或附加的方面和优点从结合下面附图对实施例的描述中将变得明显和容易理解,其中:The above and/or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of embodiments taken in conjunction with the accompanying drawings, wherein:

图1为本发明实施例的管线布置方法的步骤图。FIG. 1 is a step diagram of a pipeline arrangement method according to an embodiment of the present invention.

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,仅用于解释本发明,而不能理解为对本发明的限制。The following describes in detail the embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals refer to the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary, only used to explain the present invention, and should not be construed as a limitation of the present invention.

在本发明的描述中,需要理解的是,涉及到方位描述,例如上、下、前、后、左、右等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the azimuth description, such as the azimuth or position relationship indicated by up, down, front, rear, left, right, etc., is based on the azimuth or position relationship shown in the drawings, only In order to facilitate the description of the present invention and simplify the description, it is not indicated or implied that the indicated device or element must have a particular orientation, be constructed and operated in a particular orientation, and therefore should not be construed as limiting the present invention.

本发明的描述中,除非另有明确的限定,设置、安装、连接等词语应做广义理解,所属技术领域技术人员可以结合技术方案的具体内容合理确定上述词语在本发明中的具体含义。In the description of the present invention, unless otherwise clearly defined, words such as setting, installation, connection should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above words in the present invention in combination with the specific content of the technical solution.

下面结合附图1对本发明的实施例做进行进一步阐述:Embodiments of the present invention are further elaborated below in conjunction with accompanying drawing 1:

装配式钢结构建筑管线布置方法包括如下步骤:The pipeline layout method of prefabricated steel structure building includes the following steps:

S1:获取建筑结构图和管线走向剖面图。S1: Obtain the building structure diagram and the pipeline direction profile.

应理解的是,建筑结构图和管线走向剖面图根据施工场地测量后得到的二维平面设计图。It should be understood that the building structure drawing and the pipeline sectional drawing are based on the two-dimensional plan design drawing obtained after the construction site measurement.

S2:获取建筑结构图和管线走向剖面图对应的初始三维模型图。S2: Obtain the initial 3D model diagram corresponding to the building structure diagram and the pipeline direction section diagram.

应理解的是,初始三维模型图可以通过S1中的二维平面设计图导入三维软件中,进行建模得到。It should be understood that the initial 3D model diagram can be obtained by importing the 2D plane design diagram in S1 into the 3D software for modeling.

应理解的是,管线剖面图指的是管线走线管道的剖面图,根据管线走向剖面图,可以还原出管线在建筑中的具体走向,以及电线开槽位置。It should be understood that the sectional view of the pipeline refers to the sectional view of the pipeline routing pipeline. According to the sectional view of the pipeline direction, the specific direction of the pipeline in the building and the position of the wire slot can be restored.

S3:在初始三维模型图中,获取在钢梁和/或基墙中的管线走线需要优化的区域。S3: In the initial 3D model drawing, obtain the areas in the steel beam and/or the base wall where the pipeline routing needs to be optimized.

应理解的是,在一些实施例中,优化区域指的是基墙本身的管线走线区域;在另一些实施例中,也可以是基墙和钢梁相邻的区域。It should be understood that, in some embodiments, the optimized area refers to the pipeline routing area of the base wall itself; in other embodiments, it may also be the area adjacent to the base wall and the steel beam.

S4:在选取的区域中,根据优化规则对管线排布和/或基墙的位置进行调整优化。S4: In the selected area, adjust and optimize the pipeline arrangement and/or the position of the foundation wall according to the optimization rule.

应理解的是,优化规则的设定可以针对墙体和钢梁自身结构特征进行设定,避免管线排布造成对墙体结构和钢梁结构的破坏。It should be understood that the setting of the optimization rule can be set according to the structural characteristics of the wall and the steel beam itself, so as to avoid the damage to the wall structure and the steel beam structure caused by the pipeline arrangement.

应理解的是,优化规则也可以根据对建筑以及建筑材料的施工要求进行设定。例如,管线走线的规整程度会影响后期的维护;因此可以根据优化规则使得管线走线的有序设置,从而提升建筑的质量,避免后期维护困难以及安装五金件时破坏电线的情况。It should be understood that the optimization rules can also be set according to the construction requirements of the building and building materials. For example, the regularity of the pipeline routing will affect the later maintenance; therefore, the pipeline routing can be arranged in an orderly manner according to the optimization rules, thereby improving the quality of the building and avoiding the difficulty of later maintenance and the damage to the wires when installing hardware.

因此,可以根据建筑结构的特征,设定与本次建筑相匹配的优化规则。Therefore, according to the characteristics of the building structure, an optimization rule matching this building can be set.

S5:根据优化后的三维模型图,输出施工图纸。S5: According to the optimized 3D model drawing, output the construction drawings.

通过上述三维建模方式将建筑信息更加直观的展示,并根据以建筑结构的特征设定的管线走线规则,进行系统设计优化。此时,根据优化后的图纸施工,可以避免由于走线不合理导致返工的现象,以提升建筑的效率和质量。Through the above three-dimensional modeling method, the building information is displayed more intuitively, and the system design is optimized according to the pipeline routing rules set based on the characteristics of the building structure. At this time, the construction according to the optimized drawings can avoid the phenomenon of rework caused by unreasonable wiring, so as to improve the efficiency and quality of the building.

在一些实施例中,优化规则还包括:基墙仅有一侧墙体设置有管线走线。通过仅在墙体一侧设置管线,可以避免由于墙体双面开槽的情况,从而影响墙体的稳定性。In some embodiments, the optimization rule further includes: only one side of the base wall is provided with pipelines. By arranging pipelines only on one side of the wall, it is possible to avoid the situation that the wall is slotted on both sides, thereby affecting the stability of the wall.

应理解的是,墙体两侧开槽,如果存在施工不规范,导致开槽过深,会破坏墙体的稳定性。当使用一定年限后,墙体容易开裂或者倒塌。It should be understood that the grooves on both sides of the wall, if the construction is not standardized, lead to the groove being too deep, which will destroy the stability of the wall. When used for a certain number of years, the wall is easy to crack or collapse.

在一些实施例中,优化规则包括:基墙的位置相对于钢梁位置向外凸出,管线垂直于地面,且向上穿过基墙延伸至钢梁外侧。可以在钢梁结构无需开槽的情况下,管线可以垂直于地面向上固定在钢梁一侧。既满足管线垂直向上排布,又保证了建筑的安全性。In some embodiments, the optimization rule includes that the position of the base wall protrudes outward relative to the position of the steel beam, the pipeline is perpendicular to the ground, and extends upward through the base wall to the outside of the steel beam. The pipeline can be fixed on one side of the steel beam perpendicular to the ground without the need for grooves in the steel beam structure. It not only satisfies the vertical upward arrangement of pipelines, but also ensures the safety of the building.

应理解的是,钢梁结构的建筑应需要避免在钢梁上开槽,以免影响钢梁的承重力。因此当采取垂直于地面并向上走线方式时,基墙需要外凸于钢梁的位置,这样可以使得管线的线管穿过基墙延伸至钢梁一侧时,可以固定在钢梁一侧,从而保持钢梁的完整结构。It should be understood that, for buildings with a steel beam structure, it is necessary to avoid grooving on the steel beams, so as not to affect the bearing capacity of the steel beams. Therefore, when the line is perpendicular to the ground and upwards, the base wall needs to protrude from the position of the steel beam, so that when the line pipe of the pipeline extends through the base wall to the side of the steel beam, it can be fixed on the side of the steel beam. , thereby maintaining the complete structure of the steel beam.

应理解的是,横向开槽会影响墙面的承重力,尤其是承重墙,因此应尽量避免横向开槽来进行管线布线。同时,垂直于地面并向上走线的方式,可以快速明确线管的位置,以提升施工的效率。因此优化规则尽量采用垂直于地面并向上走线的方式,可以简化施工,同时保证建筑的安全性。It should be understood that the lateral slotting will affect the bearing capacity of the wall, especially the load-bearing wall, so the lateral slotting should be avoided as much as possible for pipeline wiring. At the same time, the way of running the line perpendicular to the ground and upward can quickly determine the position of the line pipe, so as to improve the efficiency of construction. Therefore, the optimization rules should be perpendicular to the ground and run upwards as much as possible, which can simplify the construction and ensure the safety of the building at the same time.

应理解的是,在一些实施例中,管线走线的优化既包括墙体一侧设置管线,也包括管线垂直于地面并向上走线的方式,以满足建筑对安全性和维护性的要求。在另一些实施例中,管线走线的优化仅包括墙体一侧设置管线或者管线垂直于地面并向上走线。It should be understood that, in some embodiments, the optimization of pipeline routing includes not only arranging pipelines on one side of the wall body, but also a manner in which the pipelines are perpendicular to the ground and run upwards, so as to meet the safety and maintenance requirements of the building. In other embodiments, the optimization of the pipeline routing only includes arranging pipelines on one side of the wall or the pipelines are perpendicular to the ground and run upwards.

在一些实施例中,基墙的位置向外凸出的距离为10-20mm。当设置向外凸出的距离为10-20mm时,管线垂直于地面并向上走线时,基墙不会凸出钢梁过多,从而影响整体外观。In some embodiments, the location of the base wall protrudes outward by a distance of 10-20 mm. When the outwardly protruding distance is set to 10-20mm, when the pipeline is perpendicular to the ground and runs upwards, the base wall will not protrude too much from the steel beam, thus affecting the overall appearance.

在一些实施例中,装配式钢结构建筑管线走线方法还包括如下步骤:根据施工图纸进行现场施工。通过严格按照设计好的图纸施工,可以提升建筑的效率。In some embodiments, the method for routing the pipelines of the fabricated steel structure building further includes the following steps: performing on-site construction according to the construction drawings. By strictly following the designed drawings, the efficiency of the building can be improved.

应理解的是,由于前期设计时,已将现场施工按照三维模式展示,并对其进行系统优化,因此后期严格按照图纸施工时,可以进行有效分工,并且准确高效的实施,以提升效率。It should be understood that, since the on-site construction has been displayed in a three-dimensional mode and systematically optimized in the early stage of the design, when the construction is carried out strictly in accordance with the drawings in the later stage, an effective division of labor can be carried out, and the accurate and efficient implementation can be carried out to improve efficiency.

在一些实施例中,根据施工图纸进行现场施工还包括如下步骤:In some embodiments, the on-site construction according to the construction drawings further includes the following steps:

根据施工图纸,在基墙内开槽放置线管。Slot the conduit in the base wall according to the construction drawings.

对钢梁进行填充,并进行抹灰找平。Fill the steel beams and level them with plastering.

通过在管线线管排布完成后,将钢梁进行填充和抹灰找平,可以使得线管固定在钢梁一侧,且墙体和钢梁整体更加平整美观。By filling, plastering and leveling the steel beam after the line pipe is arranged, the line pipe can be fixed on one side of the steel beam, and the wall and the steel beam as a whole are more flat and beautiful.

应理解的是,根据施工图纸以及管线的直径,可以在施工图纸中管线对应的位置进行开槽,并将电线放置管线内,置入槽中。由于基墙比钢梁凸出,因此,装有电线的管线仅靠在钢梁一侧。通过在钢梁上涂抹砂浆找平,可以进一步固定管线在钢梁上。此时,墙体和钢梁表面一侧齐平,整体建筑更加美观;而另一侧墙体微微向内凹进,后期通过简单的墙面装饰即可掩盖。It should be understood that, according to the construction drawings and the diameter of the pipeline, a slot can be made at the corresponding position of the pipeline in the construction drawing, and the electric wire can be placed in the pipeline and placed in the slot. Since the base wall is more protruding than the steel beam, the pipeline with the wires is only on one side of the steel beam. The pipeline can be further secured to the steel beam by applying mortar leveling to the steel beam. At this time, the surface of the wall and the steel beam is flush on one side, and the overall building is more beautiful; while the wall on the other side is slightly recessed inward, which can be covered by simple wall decoration in the later stage.

在一些实施例中,基墙包括ALC条板。通过ALC搭建基墙的墙体,可以提升建筑的效率。In some embodiments, the base wall includes ALC slats. Building the base wall through ALC can improve the efficiency of the building.

应理解的是,ALC条板具有可锯、切、刨、钻、干作业的特点,因此可以提升施工效率。It should be understood that ALC slats can be sawed, cut, planed, drilled and dried, thus improving construction efficiency.

应理解的是,在一些实施例中,基墙的墙体可以仅采用ALC条板。在另一些实施例中,墙体也包括水泥填充墙的墙体以及ALC条板组成的墙体。It should be understood that, in some embodiments, the walls of the base wall may employ only ALC battens. In other embodiments, the wall also includes a cement-filled wall and a wall composed of ALC slats.

在一些实施例中,优化后的三维模型图通过BIM软件获取。通过BIM,可以简化三维建筑模型中管线走线优化的过程。In some embodiments, the optimized three-dimensional model diagram is obtained by BIM software. Through BIM, the process of pipeline routing optimization in 3D building models can be simplified.

应理解的是,BIM可以自动检测图纸的问题,对碰撞问题进行协调并生成数据,如风管与梁碰撞;从而简化优化工作量,以提高工作效率。It should be understood that BIM can automatically detect problems in drawings, coordinate collision problems and generate data, such as duct and beam collisions; thus simplifying the optimization workload to improve work efficiency.

应理解的是,采用BIM,还可以使得图纸跟模型同步,还可以与后期施工单位对接,进行时间与成本的工期模拟,有错误也能及时修改,实现监督管理的目的。It should be understood that the use of BIM can also synchronize the drawings with the model, and can also connect with the later construction unit to simulate the time and cost of the construction period. If there are errors, it can be revised in time to achieve the purpose of supervision and management.

具体的,下面参考图1以一个具体的实施例详细描述根据本发明一种装配式钢结构建筑管线布置方法的施工过程。值得理解的是,下述描述仅是示例性说明,而不是对发明的具体限制。Specifically, with reference to FIG. 1 , the construction process of a method for arranging pipelines in a prefabricated steel structure building according to the present invention will be described in detail with a specific embodiment. It is to be understood that the following description is illustrative only and not specific limitation of the invention.

具体的,施工前,先对建筑物进行测量,并获得如S1中的建筑结构图、管线走线剖面图的平面设计图。接着,如图1所示,将平面设计图纸导入BIM软件中,此时可以获得S2中的建筑结构图和管线走向剖面图对应的初始三维模型图。Specifically, before construction, the building is measured first, and a plan design drawing such as the building structure drawing and the pipeline routing section drawing in S1 is obtained. Next, as shown in Figure 1, the graphic design drawings are imported into the BIM software, and the initial 3D model diagram corresponding to the building structure diagram and the pipeline profile in S2 can be obtained.

此时,可以在初始三维模型中,直观看到管线在ALC墙体、填充墙、钢梁的走线位置。At this point, in the initial 3D model, you can intuitively see the routing positions of pipelines on ALC walls, infill walls, and steel beams.

应理解的是,由于管线排布时需要开槽,会影响墙体和钢梁的结构,从而影响建筑的安全性。因此,需要对墙体和钢梁进行系统性的管线走线优化。考虑到墙体存在双面走线,而双面走线在实际施工时,需要墙体双面开槽。此时,若开槽深度过深,容易导致墙体结构不稳,后期出现坍塌的现象。因此,首先对墙体进行优化。It should be understood that, due to the need for grooving when arranging the pipeline, the structure of the wall and the steel beam will be affected, thereby affecting the safety of the building. Therefore, systematic pipeline routing optimization is required for walls and steel beams. Considering that the wall has double-sided wiring, and the double-sided wiring needs to be slotted on both sides of the wall during actual construction. At this time, if the groove depth is too deep, it is easy to cause the wall structure to be unstable and collapse in the later stage. Therefore, the wall is first optimized.

此时,进入步骤S3,在BIM选中墙体的区域,其中墙体包括填充墙和ALC墙体。At this time, go to step S3, and select the wall area in the BIM, wherein the wall includes the infill wall and the ALC wall.

接着进入步骤S4,对选中的墙体区域进行优化调整。优化规则如下:Next, step S4 is entered to optimize and adjust the selected wall area. The optimization rules are as follows:

规则一:调整墙体的双面走线为单面走向。Rule 1: Adjust the double-sided wiring of the wall to one-sided.

当优化完成后。重复步骤S3和S4进入下一优化。在本实施例中,由于部分墙体为ALC墙体,而ALC墙体多处横向开槽容易导致ALC墙体结构不稳的特质。因此选中墙体和钢梁的优化区域,进行优化。此时,针对ALC墙体进行规则二,避免对墙体进行横向开槽,优化规则如下:when optimization is complete. Repeat steps S3 and S4 to enter the next optimization. In this embodiment, since some of the walls are ALC walls, the ALC walls are easily structurally unstable due to the fact that the ALC walls have multiple transverse grooves. Therefore, the optimization area of the wall and steel beam is selected for optimization. At this time, the second rule is carried out for the ALC wall to avoid horizontal grooving of the wall. The optimization rules are as follows:

将管线在墙体内垂直地面,并向上的方式排布。Arrange the pipelines vertically in the wall and upwards.

同时,考虑到建筑的结构的钢梁为工字型钢。而仅将ALC墙体上管线垂直于地面并向上走线,需要在钢梁上开槽,以贯穿钢梁,而本实施例中采用工字型钢梁,当工字型钢梁开槽尤其是梁翼部位,会影响工字型钢的受力,从而影响建筑的安全性。At the same time, considering that the steel beam of the building's structure is I-beam. However, only if the pipelines on the ALC wall are perpendicular to the ground and run upwards, the steel beams need to be slotted to penetrate the steel beams. In this embodiment, I-shaped steel beams are used. When the I-shaped steel beams are slotted, especially It is the part of the beam and wing, which will affect the force of the I-beam, thereby affecting the safety of the building.

因此,优化规则还包括,调整ALC的墙体位置,使其凸出工字型钢梁。Therefore, the optimization rule also includes adjusting the wall position of the ALC so that it protrudes from the I-beam.

其次,考虑建筑的美观以及管线的厚度,选取凸出距离为10-20mm之间。Secondly, considering the beauty of the building and the thickness of the pipeline, the protruding distance is selected to be between 10-20mm.

此时,管线垂直于地面并向上穿过ALC墙体,靠在钢梁的一侧。At this point, the pipeline is perpendicular to the ground and goes up through the ALC wall against the side of the steel beam.

对于填充墙,由于横向走线的方式容易在后期安装五金件时破坏管线,因此对ALC墙体和钢梁的优化规则同样适用于填充墙。此时,根据规则二中的优化方式,对填充墙进行优化。For the infill wall, since the horizontal wiring is easy to damage the pipeline when installing the hardware later, the optimization rules for ALC walls and steel beams are also applicable to the infill wall. At this time, according to the optimization method in Rule 2, the infill wall is optimized.

此时,根据规则一和规则二,完成了管线的系统性优化得到优化后的三维模型,此时可以进入步骤S5输出对应的施工图纸。当获取输出的图纸后,可以根据输出的施工图纸进行现场施工。At this time, according to Rule 1 and Rule 2, the systematic optimization of the pipeline is completed to obtain an optimized three-dimensional model, and at this time, step S5 can be entered to output the corresponding construction drawings. After obtaining the output drawings, on-site construction can be carried out according to the output construction drawings.

施工时,工人严格按照输出的图纸,进行钢梁、墙体的搭建。当钢梁搭建完成后,根据图纸在ALC墙体一侧垂直于地面并向上开槽,设置线管,此时线管靠近钢梁一侧。当所有的管线均在线管中排布完成后,对钢梁进行梁窝填充,以及抹灰找平,使得钢梁和墙体一侧齐平。During construction, workers constructed steel beams and walls in strict accordance with the output drawings. When the steel beam is constructed, according to the drawings, the side of the ALC wall is perpendicular to the ground and grooved upward, and the line pipe is installed. At this time, the line pipe is close to the side of the steel beam. After all the pipelines are arranged in the line pipe, the steel beams are filled with beam pockets, and plastered and leveled, so that the steel beams are flush with one side of the wall.

尽管已经示出和描述了本发明的实施例,本领域的普通技术人员可以理解:在不脱离本发明的原理和宗旨的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由权利要求及其等同物限定。Although embodiments of the present invention have been shown and described, it will be understood by those of ordinary skill in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, The scope of the invention is defined by the claims and their equivalents.

上面结合附图对本发明实施例作了详细说明,但是本发明不限于上述实施例,在所述技术领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下做出各种变化。The embodiments of the present invention have been described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above-mentioned embodiments, and can also be made within the scope of knowledge possessed by those of ordinary skill in the technical field without departing from the purpose of the present invention. Various changes.

Claims (8)

1.一种装配式钢结构建筑管线布置方法,其特征在于,包括如下步骤:1. a method for arranging pipelines in an assembled steel structure building, is characterized in that, comprises the steps: 获取建筑结构图和管线走向剖面图;Obtain building structure drawings and pipeline orientation profiles; 获取建筑结构图和管线走向剖面图对应的初始三维模型图;Obtain the initial 3D model diagram corresponding to the building structure diagram and the pipeline direction section diagram; 在所述初始三维模型图中,获取在钢梁和/或基墙中的管线走线需要优化的区域;In the initial three-dimensional model drawing, obtain the areas where the pipeline routing in the steel beam and/or the foundation wall needs to be optimized; 在选取的区域中,根据优化规则对管线排布和/或基墙的位置进行调整优化;In the selected area, adjust and optimize the pipeline arrangement and/or the position of the foundation wall according to the optimization rules; 根据优化后的三维模型图,输出施工图纸。According to the optimized 3D model drawings, output construction drawings. 2.根据权利要求1所述的装配式钢结构建筑管线布置方法,其特征在于,所述优化规则包括:2. The prefabricated steel structure building pipeline arrangement method according to claim 1, wherein the optimization rule comprises: 所述基墙仅有一侧墙体设置有管线走线。Only one side of the base wall is provided with pipelines. 3.根据权利要求1或2所述的装配式钢结构建筑管线布置方法,其特征在于,所述优化规则包括:3. The prefabricated steel structure building pipeline arrangement method according to claim 1 or 2, wherein the optimization rule comprises: 所述基墙的位置相对于所述钢梁位置向外凸出;管线垂直于地面,且向上穿过所述基墙延伸至所述钢梁外侧。The position of the base wall protrudes outward relative to the position of the steel beam; the pipeline is perpendicular to the ground and extends upward through the base wall to the outside of the steel beam. 4.根据权利要求3所述的装配式钢结构建筑管线布置方法,其特征在于,4. The prefabricated steel structure building pipeline arrangement method according to claim 3, is characterized in that, 所述基墙的位置向外凸出的距离为10-20mm。The position of the base wall protrudes outward by a distance of 10-20mm. 5.根据权利要求3所述的装配式钢结构建筑管线布置方法,其特征在于,还包括如下步骤:5. The prefabricated steel structure building pipeline arrangement method according to claim 3, is characterized in that, also comprises the following steps: 根据施工图纸进行现场施工。On-site construction according to construction drawings. 6.根据权利要求5所述的装配式钢结构建筑管线布置方法,其特征在于,根据施工图纸进行现场施工还包括如下步骤:6. The prefabricated steel structure building pipeline arrangement method according to claim 5, wherein the on-site construction according to the construction drawings also comprises the following steps: 根据施工图纸,在所述基墙内开槽放置线管;According to the construction drawings, slot the line pipe in the base wall; 对所述钢梁进行填充,并进行抹灰找平。The steel beams are filled and leveled by plastering. 7.根据权利要求1所述的装配式钢结构建筑管线布置方法,其特征在于,7. The prefabricated steel structure building pipeline arrangement method according to claim 1, is characterized in that, 所述基墙包括ALC条板。The base wall includes ALC battens. 8.根据权利要求1所述的装配式钢结构建筑管线布置方法,其特征在于,8. The prefabricated steel structure building pipeline arrangement method according to claim 1, is characterized in that, 所述优化后的三维模型图通过BIM软件获取。The optimized three-dimensional model diagram is obtained by BIM software.
CN202010400475.5A 2020-05-13 2020-05-13 Prefabricated steel structure building pipeline layout method Pending CN111737791A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010400475.5A CN111737791A (en) 2020-05-13 2020-05-13 Prefabricated steel structure building pipeline layout method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010400475.5A CN111737791A (en) 2020-05-13 2020-05-13 Prefabricated steel structure building pipeline layout method

Publications (1)

Publication Number Publication Date
CN111737791A true CN111737791A (en) 2020-10-02

Family

ID=72647123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010400475.5A Pending CN111737791A (en) 2020-05-13 2020-05-13 Prefabricated steel structure building pipeline layout method

Country Status (1)

Country Link
CN (1) CN111737791A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112131696A (en) * 2020-11-23 2020-12-25 中国人民解放军国防科技大学 A performance optimization method and track device for an environmental control and life insurance system
CN113468702A (en) * 2021-07-22 2021-10-01 久瓴(江苏)数字智能科技有限公司 Pipeline arrangement method and device and computer readable storage medium
CN116305382A (en) * 2021-12-07 2023-06-23 中国电信国际有限公司 Three-dimensional scene-based wiring method and device, storage medium and electronic equipment
CN119442357A (en) * 2022-03-25 2025-02-14 北京达美盛软件股份有限公司 A steel structure digital restoration device and method for digital twin construction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205153395U (en) * 2015-12-04 2016-04-13 宝钢建筑系统集成有限公司 Assembled composite decoration board
CN107066750A (en) * 2017-04-26 2017-08-18 中天建设集团有限公司天津分公司 A kind of method for solving the arrangement of electrical and mechanical comprehensive pipeline
CN111143915A (en) * 2019-11-18 2020-05-12 中国化学工程第六建设有限公司 Steel structure modular installation method based on Tekla software platform
CN112948913A (en) * 2021-01-26 2021-06-11 柳州工学院 Electromechanical pipeline assembly type construction method based on BIM technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205153395U (en) * 2015-12-04 2016-04-13 宝钢建筑系统集成有限公司 Assembled composite decoration board
CN107066750A (en) * 2017-04-26 2017-08-18 中天建设集团有限公司天津分公司 A kind of method for solving the arrangement of electrical and mechanical comprehensive pipeline
CN111143915A (en) * 2019-11-18 2020-05-12 中国化学工程第六建设有限公司 Steel structure modular installation method based on Tekla software platform
CN112948913A (en) * 2021-01-26 2021-06-11 柳州工学院 Electromechanical pipeline assembly type construction method based on BIM technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
姚程渊等: ""BIM技术在装配式钢结构工程中的应用"", 《山西建筑》, vol. 42, no. 10, 15 April 2016 (2016-04-15), pages 61 - 62 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112131696A (en) * 2020-11-23 2020-12-25 中国人民解放军国防科技大学 A performance optimization method and track device for an environmental control and life insurance system
CN112131696B (en) * 2020-11-23 2021-02-26 中国人民解放军国防科技大学 A performance optimization method and track device for an environmental control and life insurance system
CN113468702A (en) * 2021-07-22 2021-10-01 久瓴(江苏)数字智能科技有限公司 Pipeline arrangement method and device and computer readable storage medium
CN113468702B (en) * 2021-07-22 2024-03-22 久瓴(江苏)数字智能科技有限公司 Pipeline arrangement method, pipeline arrangement device and computer readable storage medium
CN116305382A (en) * 2021-12-07 2023-06-23 中国电信国际有限公司 Three-dimensional scene-based wiring method and device, storage medium and electronic equipment
CN119442357A (en) * 2022-03-25 2025-02-14 北京达美盛软件股份有限公司 A steel structure digital restoration device and method for digital twin construction

Similar Documents

Publication Publication Date Title
CN111737791A (en) Prefabricated steel structure building pipeline layout method
CN106836806B (en) Constructing special-shaped concrete structure with BIM technology and its precision control method and device in the process
CN102535738A (en) A prefabricated house wall panel and a fully prefabricated house using the wall panel and its installation method
CN103726607A (en) Wall board for assembling integral shear wall, shear wall and construction method of shear wall
CN116992530A (en) Three-dimensional parameterized design and parameter database construction method for underground factory building cavern group
CN203716397U (en) Wallboard for assembling integral shear wall and shear wall
CN104032868A (en) Module floor slab assembling structure for building and process method
CN104810744A (en) Free pre-burying construction method of wall pipeline
CN121256902A (en) BIM technology-based large-area complex modeling suspended ceiling construction method
CN111608332B (en) Construction method of cast-in-place concrete roof wing-shaped angle cornice
CN107190989A (en) Shaped steel partition plate external wall construction method
CN207110029U (en) A kind of assembled house
CN205348461U (en) Empty core plate shear wall structure of assembled
CN205591394U (en) Pin -connected panel aluminium system abatvoix wall
CN116927501A (en) A collaborative construction method for deformation of asymmetric suspended curtain walls
CN205369755U (en) Prefabricated half assembled stair of ladder step
CN203546945U (en) Wallboard and shear wall with post-cast strip at floor position composed of wallboard
CN114541570A (en) Organ type outer vertical surface structure and construction method
CN119358093B (en) BIM-based prefabricated component management method and system
US20210230868A1 (en) Improvements in or relating to building structures
EP4311891A1 (en) Industrialised construction system and manufacturing process and assembly of said industrialised construction system
EP1726728B1 (en) Method of erecting a partition wall integrated with a concrete floor
RU94247U1 (en) KIT FOR FIXED FORMWORK FOR BUILDING WALLS, STRUCTURES
CN219690942U (en) Report hall barrage hyperboloid aluminum plate assembles structure and report hall barrage
CN219638236U (en) Building assembled integral hole wall board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201002