CN106323524A - Transformer high voltage bushing end linear metal fitting static state pulling force measurement system and method - Google Patents

Transformer high voltage bushing end linear metal fitting static state pulling force measurement system and method Download PDF

Info

Publication number
CN106323524A
CN106323524A CN201610687972.1A CN201610687972A CN106323524A CN 106323524 A CN106323524 A CN 106323524A CN 201610687972 A CN201610687972 A CN 201610687972A CN 106323524 A CN106323524 A CN 106323524A
Authority
CN
China
Prior art keywords
pulling force
cross beam
gold utensil
word pattern
voltage bushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610687972.1A
Other languages
Chinese (zh)
Other versions
CN106323524B (en
Inventor
谢凯
吕中宾
钱诗林
寇晓适
张嵩阳
吴豫
蔡永平
李梦丽
任鹏亮
魏建林
王伟
王朝华
付刚
付海金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Henan Electric Power Co Ltd
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
State Grid Henan Electric Power Co Ltd
Electric Power Research Institute of State Grid Henan Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Henan Electric Power Co Ltd, Electric Power Research Institute of State Grid Henan Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical State Grid Henan Electric Power Co Ltd
Priority to CN201610687972.1A priority Critical patent/CN106323524B/en
Publication of CN106323524A publication Critical patent/CN106323524A/en
Application granted granted Critical
Publication of CN106323524B publication Critical patent/CN106323524B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • G01L5/0028Force sensors associated with force applying means
    • G01L5/0033Force sensors associated with force applying means applying a pulling force
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L1/00Measuring force or stress, in general
    • G01L1/20Measuring force or stress, in general by measuring variations in ohmic resistance of solid materials or of electrically-conductive fluids; by making use of electrokinetic cells, i.e. liquid-containing cells wherein an electrical potential is produced or varied upon the application of stress
    • G01L1/22Measuring force or stress, in general by measuring variations in ohmic resistance of solid materials or of electrically-conductive fluids; by making use of electrokinetic cells, i.e. liquid-containing cells wherein an electrical potential is produced or varied upon the application of stress using resistance strain gauges
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • G01L5/16Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes for measuring several components of force
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • G01L5/16Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes for measuring several components of force
    • G01L5/161Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes for measuring several components of force using variations in ohmic resistance

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Force Measurement Appropriate To Specific Purposes (AREA)

Abstract

The invention discloses a transformer high voltage bushing end linear metal fitting static state pulling force measurement system and method. A frame body comprises an upper cross beam, a lower cross beam, a left cross beam and a right cross beam; two holes are respectively formed on the upper cross beam and the lower cross beam in the horizontal direction; the middle part of the frame body is provided with a middle cross beam; two holes are formed on the middle cross beam in the horizontal direction; the holes of the upper cross beam, the middle cross beam and the lower cross beam are corresponded in a vertical direction; the middle cross beam comprises a fixing part and two connection parts; the two ends of the fixing part are arranged on the frame body through the connection parts; the top of the fixing part is higher than the upper cross beam and the lower cross beam in the horizontal direction; the bottom of the fixing part is lower than the upper cross beam and the lower cross beam in the horizontal direction; and the upper cross beam, the lower cross beam, the left cross beam, the right cross beam and the connection part are provided with pulling force sensors. The transformer high voltage bushing end linear metal fitting static state pulling force measurement system and method solve a problem that the force on the transformer high voltage bushing end linear metal fitting is hard to detect, and can realize convenient, real-time and accurate detection of the pulling force of the linear metal fitting.

Description

变压器高压套管端部一字型金具静态拉力测量系统及方法Static tension measurement system and method for one-shaped fittings at the end of transformer high-voltage bushing

技术领域technical field

本发明涉及电力领域,具体涉及一种变压器高压套管端部一字型金具静态拉力测量系统及方法。The invention relates to the field of electric power, in particular to a system and method for measuring the static tension of an in-line fitting at the end of a high-voltage bushing of a transformer.

背景技术Background technique

金具是送电线广泛使用的铁制或铝制金属附件,大部分金具在运行中需要承受较大的拉力,有的还要同时保证电气方面接触良好。特高压变电站变压器套管端部接线金具由于设计不合理、套管端部接线柱盖板强度不足、密封设计存在薄弱环节等问题,导致套管顶部接线柱的横向受力超过设计值,长期作用下导致套管端部变形后密封失效后进水,最终导致主变发生匝间短路故障。为了分析套管端部接线金具受力情况,目前主要采用仿真分析的方法,但仿真分析需设定多个假设条件,不能充分反映实际受力情况,并且不能得到实验数据验证,指导改造存在较大风险,因而需要开展实物试验,为优化设计提供依据。由于套管端部接线金具形状特殊,目前未有很好的测试方法及装置,大多是直接人工操作使用传感器进行检测,因此开展实物应力试验困难,无法实时采集拉力信息。Fittings are iron or aluminum metal accessories widely used in power transmission lines. Most of the fittings need to withstand large tension during operation, and some of them must also ensure good electrical contact. Due to the unreasonable design of the wiring fittings at the end of the bushing of the UHV substation, the insufficient strength of the cover plate of the terminal at the end of the bushing, and the weak link in the sealing design, the lateral force of the terminal at the top of the bushing exceeds the design value, and the long-term effect Under the circumstances, the end of the bushing is deformed, the seal fails, and water enters, which eventually leads to an inter-turn short circuit fault in the main transformer. In order to analyze the force of the wiring fittings at the end of the bushing, the simulation analysis method is mainly used at present, but the simulation analysis needs to set multiple assumptions, which cannot fully reflect the actual force situation, and cannot be verified by experimental data. Therefore, it is necessary to carry out physical experiments to provide a basis for optimal design. Due to the special shape of the wiring fittings at the end of the bushing, there are no good testing methods and devices at present, and most of them are detected by direct manual operation using sensors. Therefore, it is difficult to carry out physical stress tests and it is impossible to collect tension information in real time.

申请号为200820054261.1的发明公开了一种变压器高压套管及低压端子板试压试温装置,在支架上设有油箱,在油箱上设有能安装变压器高压套管的高压连接体和能安装变压器低压侧端子板的低压连接体,在油箱上还设有上下通气孔和观察孔、加热装置和温度传感器,在所述的支架上设有控制箱,控制箱与加热装置和温度传感器电连接。该发明可以对变压器高压套管进行密封和高温试验,但不能检测套管端部金具的拉力参数。申请号为201320839446.4的发明专利公开了一种高压套管末屏传感器,包括雷电冲击保护模块、快速接地模块、开路限压保护模块、检测输出电压,雷电冲击保护模块在检测输出电压超过限值后将检测输出电压通过快速接地模块引入大地,开路限压保护模块调节检测输出电压的输出范围。但该传感器仅能检测电力设备套管的电压参数,不能检测套管端部金具的拉力参数,无法判断套管顶部接线柱的横向受力是否超过设计值,不能得到套管金具的实际受力情况。The invention with the application number of 200820054261.1 discloses a transformer high-voltage bushing and low-voltage terminal board pressure and temperature test device. An oil tank is provided on the bracket, and a high-voltage connector capable of installing the transformer high-voltage bushing and a transformer can be installed on the oil tank. The low-voltage connection body of the low-voltage side terminal board is also provided with upper and lower ventilation holes and observation holes, a heating device and a temperature sensor on the fuel tank, and a control box is provided on the support, and the control box is electrically connected with the heating device and the temperature sensor. The invention can carry out sealing and high-temperature tests on the high-voltage bushing of the transformer, but cannot detect the tension parameter of the fittings at the end of the bushing. The invention patent with the application number 201320839446.4 discloses a high-voltage bushing end screen sensor, including a lightning impulse protection module, a fast grounding module, an open circuit voltage limiting protection module, and a detection output voltage. After the lightning impulse protection module detects that the output voltage exceeds the limit The detection output voltage is introduced into the ground through the fast grounding module, and the open circuit voltage limiting protection module adjusts the output range of the detection output voltage. However, the sensor can only detect the voltage parameters of the bushing of the power equipment, but cannot detect the tension parameters of the fittings at the end of the bushing, cannot judge whether the lateral force of the terminal on the top of the bushing exceeds the design value, and cannot obtain the actual force of the fittings of the bushing Condition.

发明内容Contents of the invention

有鉴于此,本发明提供了一种变压器高压套管端部一字型金具静态拉力测量系统及方法,解决了现有变电站变压器套管端部一字型金具实际受力难以检测的问题,能够实现一字型金具拉力的方便、实时、精确检测,以便监测一字型金具的使用状况,进行及时检修或更换。In view of this, the present invention provides a static tension measuring system and method for the in-line fittings at the end of transformer high-voltage bushings, which solves the problem that it is difficult to detect the actual force of the in-line fittings at the end of transformer bushings in existing substations, and can Realize the convenient, real-time and accurate detection of the pulling force of the inline fittings, so as to monitor the use status of the inline fittings and carry out timely maintenance or replacement.

本发明采用以下技术方案:The present invention adopts following technical scheme:

一种变压器高压套管端部一字型金具静态拉力测量系统,其中,包括框体,所述框体包括上横梁、下横梁、左横梁和右横梁,所述框体的上横梁和下横梁均在水平方向设置两个孔,所述框体中部设置有中横梁,所述中横梁在水平方向设置两个孔,所述上横梁、中横梁和下横梁的孔在竖直方向对应;所述中横梁包括固定部和两个连接部,所述固定部两端经连接部设置在框体上,所述固定部的顶部在水平方向高于所述上横梁和下横梁,底部在水平方向低于所述上横梁和下横梁;所述上横梁、下横梁、左横梁、右横梁及连接部均设有拉力传感器。A static tension measurement system for in-line fittings at the end of a high-voltage bushing of a transformer, including a frame, the frame includes an upper beam, a lower beam, a left beam, and a right beam, and the upper beam and the lower beam of the frame are Both are provided with two holes in the horizontal direction, the middle part of the frame body is provided with a middle beam, and the middle beam is provided with two holes in the horizontal direction, and the holes of the upper beam, the middle beam and the lower beam are corresponding in the vertical direction; The middle crossbeam includes a fixed part and two connecting parts, the two ends of the fixed part are arranged on the frame body through the connecting part, the top of the fixed part is higher than the upper crossbeam and the lower crossbeam in the horizontal direction, and the bottom is in the horizontal direction Lower than the upper beam and the lower beam; the upper beam, the lower beam, the left beam, the right beam and the connecting parts are all equipped with tension sensors.

优选的,所述每个连接部均设置有拉力传感器。Preferably, each connection part is provided with a tension sensor.

优选的,所述连接部内设置四个拉力传感器,所述的四个拉力传感器均匀分布在连接部的四周。Preferably, four tension sensors are arranged in the connection part, and the four tension sensors are evenly distributed around the connection part.

优选的,所述上横梁、下横梁、左横梁和右横梁上均设有两个凹槽,所述拉力传感器设置在凹槽内。Preferably, two grooves are provided on the upper beam, the lower beam, the left beam and the right beam, and the tension sensor is arranged in the groove.

优选的,所述凹槽内在竖直方向设置两个拉力传感器。Preferably, two tension sensors are arranged vertically in the groove.

优选的,所述上横梁和下横梁上均设有向内的凸块,所述上横梁和下横梁的两个孔分别设在相应的凸块上。Preferably, the upper beam and the lower beam are provided with inward projections, and the two holes of the upper beam and the lower beam are respectively provided on the corresponding projections.

优选的,所述连接部的厚度小于所述框体。Preferably, the thickness of the connecting portion is smaller than that of the frame body.

优选的,所述变压器高压套管端部一字型金具静态拉力测量系统还包括数显表,所述数显表与框体上设置的接线柱连接,所述接线柱与拉力传感器电连接。Preferably, the static tension measurement system for the in-line fittings at the end of the high voltage transformer bushing further includes a digital display meter, the digital display meter is connected to a terminal provided on the frame, and the terminal is electrically connected to the tension sensor.

优选的,所述变压器高压套管端部一字型金具静态拉力测量系统还包括电源,所述电源与框体上设置的接线柱连接,所述接线柱与拉力传感器电连接。Preferably, the static tension measurement system for the in-line fittings at the end of the transformer high voltage bushing further includes a power supply, the power supply is connected to a terminal provided on the frame, and the terminal is electrically connected to the tension sensor.

一种变压器高压套管端部一字型金具静态拉力测量方法,其中,包括如下步骤:A method for measuring the static tension of an in-line fitting at the end of a transformer high-voltage bushing, comprising the following steps:

步骤1,在框体的上横梁、下横梁、左横梁、右横梁及连接部均设置拉力传感器,所述上横梁与下横梁设置的拉力传感器测量一字型金具在Y方向的受力;所述左横梁与右横梁设置的拉力传感器测量一字型金具在X方向的受力;所述连接部内设置的拉力传感器测量一字型金具在Z方向的受力;Step 1, set tension sensors on the upper beam, lower beam, left beam, right beam and connecting parts of the frame, the tension sensors set on the upper beam and the lower beam measure the force of the in-line fittings in the Y direction; The tension sensors arranged on the left beam and the right beam measure the force of the in-line fittings in the X direction; the tension sensors arranged in the connecting part measure the force of the in-line fittings in the Z direction;

步骤2,将变压器高压套管端部一字型金具静态拉力测量系统设置在一字型金具上,由拉力传感器检测一字型金具的受力情况,获取拉力参数值;Step 2. Set the static tension measurement system of the inline fittings at the end of the high-voltage bushing of the transformer on the inline fittings, and use the tension sensor to detect the stress of the inline fittings to obtain the tension parameter value;

步骤3,输出各个传感器获取的拉力参数值,对测量X方向、Y方向、Z方向受力的拉力传感器分别求取平均值,得到一字型金具在X方向、Y方向、Z方向的拉力参数值。Step 3: Output the tension parameter values obtained by each sensor, calculate the average value of the tension sensors measuring the force in the X direction, Y direction, and Z direction respectively, and obtain the tension parameters of the in-line fittings in the X direction, Y direction, and Z direction value.

本发明具有以下有益效果:The present invention has the following beneficial effects:

本发明在框体上以及连接部上均设置多个拉力传感器,上横梁及下横梁上设置的拉力传感器可测量轴向(Y方向)受力情况,左、右横梁上设置的拉力传感器可测量横向(X方向)受力情况,连接部上设置的拉力传感器可测量垂直方向(Z方向)受力情况,检测每个方向受力的传感器均为多个,多个传感器测得的拉力值求取平均值,得到最终的拉力值,避免了采用单个传感器由于受力不均造成的测量结果不准确,提高了测量精确。In the present invention, a plurality of tension sensors are arranged on the frame body and the connecting part. The tension sensors arranged on the upper beam and the lower beam can measure the axial (Y direction) stress, and the tension sensors installed on the left and right beams can measure For the force in the lateral direction (X direction), the tension sensor installed on the connecting part can measure the force in the vertical direction (Z direction). There are multiple sensors for detecting the force in each direction. The tension value measured by multiple sensors is The average value is taken to obtain the final tension value, which avoids the inaccurate measurement results caused by the uneven force of a single sensor and improves the measurement accuracy.

本发明中横梁的拉力传感器测量Z方向受力情况,中横梁包括两端的连接部和中间的固定部,连接部的厚度小于固定部及框体,本发明的正面,固定部在水平方向高出上横梁及下横梁,本发明的背面,固定部低于上横梁及下横梁。本发明的中横梁采用这种悬空结构,连接部不接触待测体,当施加外力时,固定部的正面受力,力由固定部传导到两侧的连接部上,测试的范围更广。同时,两个连接部内均设置拉力传感器,且拉力传感器为多个,通过多个传感器测得的参数值求取平均值,得到Z方向的受力情况,测量精度更高。The tension sensor of the crossbeam in the present invention measures the stress situation in the Z direction. The middle crossbeam includes connecting parts at both ends and a fixed part in the middle. The thickness of the connecting part is smaller than the fixed part and the frame body. The upper cross beam and the lower cross beam, the back side of the present invention, the fixed part is lower than the upper cross beam and the lower cross beam. The central crossbeam of the present invention adopts such a suspended structure, and the connection part does not touch the object to be tested. When an external force is applied, the front of the fixed part is stressed, and the force is transmitted from the fixed part to the connection parts on both sides, and the test range is wider. At the same time, tension sensors are installed in the two connecting parts, and there are multiple tension sensors. The average value of the parameter values measured by multiple sensors is calculated to obtain the force situation in the Z direction, and the measurement accuracy is higher.

本发明能够实时检测一字型金具的受力情况,当获取的拉力参数值大于预设的最大值时,判断一字型金具可能发生断裂,将报警信息和位置信息发送给监控中心,监控中心记录后派出检修人员到现场检修。也可同时给检修人员发送报警短信或发送到检修人员的手机APP上,检修人员到现场检修后将处理情况反馈给监控中心,由监控中心记录。The present invention can detect the force condition of the inline fittings in real time, and when the acquired tension parameter value is greater than the preset maximum value, it is judged that the inline fittings may break, and the alarm information and position information are sent to the monitoring center, and the monitoring center After recording, send maintenance personnel to the scene for maintenance. It can also send an alarm message to the maintenance personnel at the same time or send it to the mobile phone APP of the maintenance personnel. After the maintenance personnel go to the site for maintenance, they will feed back the processing situation to the monitoring center, and the monitoring center will record it.

本发明解决了现有变电站变压器套管端部接线金具实际受力情况的检测难问题,避免了当金具横向受力过大可能发生断裂时,因不能够及时发现、进行检修或更换导致主变发生匝间短路故障的问题;本发明方便了检修和测试工作,降低了人力成本。The invention solves the problem of difficult detection of the actual stress of the existing substation transformer bushing end wiring fittings, and avoids the failure of the main transformer due to failure to detect, repair or replace the fittings when the fittings are too laterally stressed and may break. The problem of inter-turn short-circuit fault occurs; the invention facilitates maintenance and testing work, and reduces labor costs.

本发明的其他优点、目标和特征在某种程度上将在随后的说明书中进行阐述,并且在某种程度上,基于对下文的考察研究对本领域技术人员而言将是显而易见的,或者可以从本发明的实践中得到教导。本发明的目标和其他优点可以通过下面的说明书或者附图中所特别指出的结构来实现和获得。Other advantages, objects and features of the present invention will be set forth in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the investigation and research below, or can be obtained from It is taught in the practice of the present invention. The objectives and other advantages of the invention may be realized and attained by the structure particularly pointed out in the following description or appended drawings.

附图说明Description of drawings

图1为本发明变压器高压套管端部一字型金具静态拉力测量系统的主视结构示意图。Fig. 1 is a schematic diagram of the front view of the static tension measuring system for the inline fittings at the end of the transformer high voltage bushing according to the present invention.

图2为图1的仰视结构示意图。FIG. 2 is a schematic bottom view of the structure of FIG. 1 .

图3为图1的左视结构示意图。FIG. 3 is a schematic structural diagram of the left view of FIG. 1 .

图4为本发明变压器高压套管端部一字型金具静态拉力测量系统的传感器布置及接线示意图。Fig. 4 is a schematic diagram of the sensor layout and wiring of the static tension measurement system for the in-line fittings at the end of the transformer high voltage bushing according to the present invention.

图5为图4的A-A剖示结构示意图。FIG. 5 is a schematic diagram of the cross-sectional structure along line A-A of FIG. 4 .

图6为图4的B-B剖示结构示意图。FIG. 6 is a schematic diagram of the cross-sectional structure along line B-B of FIG. 4 .

图7为本发明变压器高压套管端部一字型金具静态拉力测量系统的使用状态示意图。Fig. 7 is a schematic diagram of the use state of the static tension measuring system for the inline fittings at the end of the transformer high voltage bushing according to the present invention.

图8为本发明变压器高压套管端部一字型金具静态拉力测量方法的流程图。Fig. 8 is a flow chart of the method for measuring the static tension of the in-line fitting at the end of the transformer high voltage bushing according to the present invention.

图9为本发明变压器高压套管端部一字型金具静态拉力测量方法另一实施方式的流程图。Fig. 9 is a flow chart of another embodiment of the method for measuring the static tension of the in-line fitting at the end of the transformer high voltage bushing according to the present invention.

具体实施方式detailed description

以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。The preferred embodiments of the present invention will be described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described here are only used to illustrate and explain the present invention, and are not intended to limit the present invention.

如图1-图6所示,本发明提供一种变压器高压套管端部一字型金具静态拉力测量系统,包括框体2,框体2包括上横梁、下横梁、左横梁和右横梁,框体的上横梁和下横梁均在水平方向设置两个孔4。框体中部设置有中横梁,中横梁包括固定部7和两个连接部6,固定部7两端经连接部6分别设置在框体的左横梁和右横梁上。固定部7在水平方向设置两个孔4,上横梁、中横梁和下横梁的孔4在竖直方向对应。As shown in Fig. 1-Fig. 6, the present invention provides a static tension measurement system for inline fittings at the end of high voltage transformer bushings, including a frame body 2, which includes an upper beam, a lower beam, a left beam and a right beam, Both the upper beam and the lower beam of the frame body are provided with two holes 4 in the horizontal direction. A middle crossbeam is arranged in the middle of the frame, and the middle crossbeam includes a fixing part 7 and two connecting parts 6, and the two ends of the fixing part 7 are respectively arranged on the left and right crossbeams of the frame through the connecting parts 6. The fixing part 7 is provided with two holes 4 in the horizontal direction, and the holes 4 of the upper crossbeam, the middle crossbeam and the lower crossbeam are corresponding in the vertical direction.

固定部7的顶部在水平方向高于上横梁和下横梁,底部在水平方向低于上横梁和下横梁,上横梁、下横梁、左横梁、右横梁及连接部6均设有拉力传感器。连接部6的厚度小于框体和固定部7。中横梁采用这种悬空结构,连接部6不接触待测体,当施加外力时,固定部7的正面(顶部)受力,力由固定部7传导到两侧的连接部6上,通过连接部6内的拉力传感器602测量待测体(一字型金具)Z方向受力情况,这种结构的测试范围更广,测量精度更高。同时,两个连接部内均设置拉力传感器,且拉力传感器为多个,通过多个传感器测得的参数值求取平均值,得到Z方向的受力情况,测量精度更高。The top of the fixed part 7 is higher than the upper beam and the lower beam in the horizontal direction, and the bottom is lower than the upper beam and the lower beam in the horizontal direction. The upper beam, the lower beam, the left beam, the right beam and the connecting part 6 are all provided with tension sensors. The thickness of the connecting part 6 is smaller than that of the frame body and the fixing part 7 . The middle beam adopts this suspended structure, and the connecting part 6 does not touch the object to be tested. When an external force is applied, the front (top) of the fixed part 7 is stressed, and the force is transmitted from the fixed part 7 to the connecting parts 6 on both sides. The tension sensor 602 in part 6 measures the force in the Z direction of the object to be tested (inline fittings). This structure has a wider test range and higher measurement accuracy. At the same time, tension sensors are installed in the two connecting parts, and there are multiple tension sensors. The average value of the parameter values measured by multiple sensors is calculated to obtain the force situation in the Z direction, and the measurement accuracy is higher.

在一个实施例中,可先在框体上需要安装拉力传感器的位置设置凹槽,然后将相应的拉力传感器埋设在凹槽内。例如,为测量Y方向(轴向)受力情况,在上横梁和下横梁上设置凹槽301,本实施例中,上横梁和下横梁的凹槽301均为两个,如图4-图6所示,在每个凹槽301内沿垂直方向设置两个拉力传感器302,这8个拉力传感器302分别测量一字型金具Y方向的受力值,求取平均值,最终的平均值即为一字型金具在Y方向的受力值。在左横梁和右横梁上设置凹槽101,凹槽101均为两个,在每个凹槽101内沿垂直方向设置两个拉力传感器102,这8个拉力传感器102分别测量一字型金具X方向的受力值,求取平均值,最终的平均值即为一字型金具在X方向的受力值。In one embodiment, a groove can be firstly provided on the frame body at the position where the tension sensor needs to be installed, and then the corresponding tension sensor can be buried in the groove. For example, in order to measure the force in the Y direction (axial direction), grooves 301 are provided on the upper beam and the lower beam. In this embodiment, there are two grooves 301 on the upper beam and the lower beam, as shown in Figure 4- As shown in 6, two tension sensors 302 are arranged vertically in each groove 301, and these eight tension sensors 302 respectively measure the force value of the in-line fittings in the Y direction, and calculate the average value, and the final average value is It is the force value of the straight fittings in the Y direction. There are two grooves 101 on the left beam and the right beam. Two tension sensors 102 are arranged in each groove 101 along the vertical direction. These 8 tension sensors 102 measure the in-line fitting X respectively. Calculate the average value of the force value in the X direction, and the final average value is the force value of the straight fittings in the X direction.

X方向(横向)、Y方向(轴向)、Z方向(垂直方向)分别代表空间直角坐标系的X轴、Y轴、Z轴方向。The X direction (horizontal direction), the Y direction (axial direction), and the Z direction (vertical direction) respectively represent the X-axis, Y-axis, and Z-axis directions of the spatial rectangular coordinate system.

在每个连接部6内分别设置个拉力传感器602,四个拉力传感器602均匀分布在连接部6的四周。这8个拉力传感器602分别测量一字型金具Z方向的受力值,求取平均值,最终的平均值即为一字型金具在Z方向的受力值。One tension sensor 602 is respectively arranged in each connecting portion 6 , and four tension sensors 602 are evenly distributed around the connecting portion 6 . The eight tension sensors 602 respectively measure the force value of the inline fittings in the Z direction, and calculate the average value, and the final average value is the force value of the inline fittings in the Z direction.

在一个实施例中,在框体的上横梁和下横梁上均设有向内的凸块5,上横梁和下横梁的两个孔4分别设在相应的凸块5上。两个凸块5与固定部7水平平行设置。固定部7的顶部在水平方向高于凸块5,底部在水平方向低于凸块5,连接部6的厚度小于框体和固定部7。这样,在本发明的正面,固定部7较高,在本发明的背面,固定部7位置较低,连接部6无论是在正面还是背面,其高度都较低,在施加垂直方向的力时,固定部7直接受力,力传导到两侧的连接部6,由连接部6内设置的拉力传感器602检测拉力值。In one embodiment, inward projections 5 are provided on the upper and lower beams of the frame, and the two holes 4 of the upper and lower beams are respectively provided on the corresponding projections 5 . The two protrusions 5 are arranged horizontally and parallel to the fixing part 7 . The top of the fixing part 7 is higher than the protrusion 5 in the horizontal direction, and the bottom is lower than the protrusion 5 in the horizontal direction, and the thickness of the connecting part 6 is smaller than that of the frame body and the fixing part 7 . Like this, on the front of the present invention, the fixed part 7 is higher, and on the back side of the present invention, the fixed part 7 position is lower, and no matter the connection part 6 is on the front or the back, its height is all low. , the fixing part 7 receives force directly, and the force is transmitted to the connection parts 6 on both sides, and the tension sensor 602 provided in the connection part 6 detects the tension value.

在一个实施例中,变压器高压套管端部一字型金具静态拉力测量系统还包括数显表,数显表与框体上设置的接线柱连接,接线柱与拉力传感器电连接。图4为本发明传感器接线布置示意图,箭头方向代表引线方向,在框体内开线槽,电线设置在线槽内,各个传感器与接线柱通过电线连接。在测量一字型金具的受力情况时,数显表可显示测得的拉力值,方便工作人员记录。In one embodiment, the static tension measuring system for the in-line fittings at the end of the high voltage transformer bushing further includes a digital display meter connected to a terminal provided on the frame, and the terminal is electrically connected to the tension sensor. Fig. 4 is a schematic diagram of the wiring layout of the sensor of the present invention, the direction of the arrow represents the direction of the lead wire, a wire slot is opened in the frame, the wires are arranged in the wire slot, and each sensor is connected to the terminal through the wire. When measuring the force of the straight fittings, the digital display can display the measured tension value, which is convenient for the staff to record.

在一个实施例中,变压器高压套管端部一字型金具静态拉力测量系统还包括电源,电源与框体上设置的接线柱8连接,接线柱与拉力传感器电连接。电源为拉力传感器和数显表供电。电源可以为锂电池。In one embodiment, the static tension measurement system for the in-line fittings at the end of the high voltage transformer bushing further includes a power supply, which is connected to the terminal 8 provided on the frame, and the terminal is electrically connected to the tension sensor. The power supply supplies power to the tension sensor and the digital display. The power source can be a lithium battery.

如图8所示,一种变压器高压套管端部一字型金具静态拉力测量方法,其中,包括如下步骤:As shown in Figure 8, a method for measuring the static tension of the in-line fittings at the end of a transformer high-voltage bushing includes the following steps:

步骤1,在框体的上横梁、下横梁、左横梁、右横梁及连接部均设置拉力传感器,所述上横梁与下横梁设置的拉力传感器测量一字型金具在Y方向的受力;所述左横梁与右横梁设置的拉力传感器测量一字型金具在X方向的受力;所述连接部内设置的拉力传感器测量一字型金具在Z方向的受力;Step 1, set tension sensors on the upper beam, lower beam, left beam, right beam and connecting parts of the frame, the tension sensors set on the upper beam and the lower beam measure the force of the in-line fittings in the Y direction; The tension sensors arranged on the left beam and the right beam measure the force of the in-line fittings in the X direction; the tension sensors arranged in the connecting part measure the force of the in-line fittings in the Z direction;

步骤2,将变压器高压套管端部一字型金具静态拉力测量系统设置在一字型金具上,由拉力传感器检测一字型金具的受力情况,获取拉力参数值;Step 2. Set the static tension measurement system of the inline fittings at the end of the high-voltage bushing of the transformer on the inline fittings, and use the tension sensor to detect the stress of the inline fittings to obtain the tension parameter value;

步骤3,输出各个传感器获取的拉力参数值,将拉力传感器按照X方向、Y方向、Z方向的分类,对测量X方向、Y方向、Z方向受力的拉力传感器分别求取平均值,得到一字型金具在X方向、Y方向、Z方向的拉力参数值。Step 3, output the tension parameter values obtained by each sensor, classify the tension sensors according to the X direction, Y direction, and Z direction, and calculate the average value of the tension sensors that measure the force in the X direction, Y direction, and Z direction respectively, and obtain a The tensile parameter values of the font fittings in the X direction, Y direction and Z direction.

电阻应变测试法的基本原理是用电阻应变片测定构件表面的线应变,再根据应变—应力关系确定构件表面应力状态的一种实验应力分析方法。这种方法是将电阻应变片粘贴的被测构件表面,当构件变形时,电阻应变片的电阻值将发生相应的变化,然后通过电阻应变仪将此电阻变化转换成电压(或电流)的变化,再换算成应变值或者输出与此应变成正比的电压(或电流)的信号,由记录仪进行记录,就可得到所测定的应变或应力。The basic principle of the resistance strain test method is an experimental stress analysis method that uses resistance strain gauges to measure the linear strain on the surface of the component, and then determines the stress state of the component surface according to the strain-stress relationship. This method is to paste the resistance strain gauge on the surface of the component under test. When the component is deformed, the resistance value of the resistance strain gauge will change accordingly, and then the resistance change is converted into a voltage (or current) change by the resistance strain gauge. , and then convert it into a strain value or output a voltage (or current) signal proportional to the strain, and record it with a recorder to obtain the measured strain or stress.

电阻应变效应的理论公式为:The theoretical formula for the resistance strain effect is:

式中:In the formula:

ρ为电阻率(Ω·mm2/m);ρ is resistivity (Ω·mm 2 /m);

L为金属丝的长度(m);L is the length of the metal wire (m);

S为金属丝的截面积(mm2);S is the cross-sectional area of the metal wire (mm 2 );

由上式可知,金属丝在承受应力而发生机械变形的过程中,ρ、L、S三者都要发生变化,从而必然会引起金属丝电阻值的变化。当受外力伸张时,长度增加,截面积减小,电阻值增加;当受压力缩短时,长度减小,截面积增大,电阻值减小。因此,只要能测出电阻值的变化,便可金属丝的应变情况。这种转换关系为:It can be seen from the above formula that during the process of mechanical deformation of the metal wire under stress, ρ, L, and S will all change, which will inevitably cause changes in the resistance value of the metal wire. When stretched by external force, the length increases, the cross-sectional area decreases, and the resistance value increases; when the pressure is shortened, the length decreases, the cross-sectional area increases, and the resistance value decreases. Therefore, as long as the change of the resistance value can be measured, the strain of the metal wire can be determined. This conversion relationship is: .

式中: 为金属丝电阻值的变化量;K0为金属材料的应变灵敏系数,它主要由试验方法确定,且在弹性极限内基本为常数;ε为金属材料的轴向应变值,因此又称长度应变值,对于金属丝而言,其值在0.24~0.4之间。In the formula: is the variation of the resistance value of the metal wire; K 0 is the strain sensitivity coefficient of the metal material, which is mainly determined by the test method and is basically constant within the elastic limit; ε is the axial strain value of the metal material, so it is also called the length strain Value, for metal wire, its value is between 0.24 and 0.4.

在实际应用中,将金属电阻应变片粘贴在传感器弹性元件或被测机械零件的表面。当传感器中的弹性元件或被测机械零件受作用力产生应变时,粘贴在其上的应变片也随之发生相同的机械变形,引起应变片电阻发生相应的变化。这时,电阻应变片便将力学量转换为电阻的变化量输出。In practical applications, the metal resistance strain gauge is pasted on the surface of the elastic element of the sensor or the mechanical part to be tested. When the elastic element in the sensor or the mechanical part under test is subjected to force to generate strain, the strain gauge pasted on it will also undergo the same mechanical deformation, causing a corresponding change in the resistance of the strain gauge. At this time, the resistance strain gauge converts the mechanical quantity into the output of the change of resistance.

一字型金具静态拉力测量系统在框体上开设与一字型金具上的孔相对应的螺孔,且螺孔的直径小于一字型金具的孔的直径,使用时采用螺栓固定,同时因为螺孔的孔径较小,方便安装固定,避免了在固定时能够通过螺孔的螺栓无法穿过一字型金具的孔。该实施例中,拉力传感器的具体参数:量程:X、Y、Z三个方向都是5000N;精度:千分之五;电源:24V;输出:0-5V。The static tension measurement system for inline fittings sets screw holes corresponding to the holes in inline fittings on the frame, and the diameter of the screw holes is smaller than the diameter of the holes in inline fittings. The aperture of the screw hole is small, which is convenient for installation and fixing, and avoids that the bolt that can pass through the screw hole cannot pass through the hole of the straight fitting when fixing. In this embodiment, the specific parameters of the tension sensor: range: 5000N in X, Y, and Z directions; accuracy: 5/1000; power supply: 24V; output: 0-5V.

根据一字形变压器套管端部接线金具的形状,制作特定尺寸的本发明一字型金具静态拉力测量系统。如图7所示,将一字型金具静态拉力测量系统9首通过直径为M12的螺栓分别固定在套管10的左右两侧一字型金具11上,然后将导线线夹同样通过M12的螺栓固定在制作的一字型金具静态拉力测量系统9上,固定好变压器套管端部一字型金具11、一字型金具静态拉力测量系统9、导线线夹后,变压器套管端部一字型金具11的受力情况即可通过一字型金具静态拉力测量系统9中拉力传感器的变化得以体现,即可实时测试出变压器套管端部一字型金具所承受的应力,并通过数显表头输出。According to the shape of the connection fittings at the end of the inline transformer bushing, a static tension measuring system for the inline fittings of the present invention with a specific size is produced. As shown in Figure 7, the 9 in-line fitting static tension measurement systems are respectively fixed to the in-line fittings 11 on the left and right sides of the bushing 10 through bolts with a diameter of M12, and then the wire clamps are also passed through the M12 bolts Fix it on the made in-line fitting static tension measuring system 9, and fix the in-line fitting 11 at the end of the transformer bushing, the in-line fitting static tension measuring system 9, and the wire clamp, and the in-line fitting at the end of the transformer bushing The force condition of the inline fittings 11 can be reflected by the change of the tension sensor in the static tension measuring system 9 of the inline fittings, and the stress borne by the inline fittings at the end of the transformer bushing can be tested in real time, and can be measured through the digital display header output.

在一个实施例中,如图9所示,本发明包括如下步骤:In one embodiment, as shown in Figure 9, the present invention includes the following steps:

步骤1,在框体的上横梁、下横梁、左横梁、右横梁及连接部均设置拉力传感器,所述上横梁与下横梁设置的拉力传感器测量一字型金具在Y方向的受力;所述左横梁与右横梁设置的拉力传感器测量一字型金具在X方向的受力;所述连接部内设置的拉力传感器测量一字型金具在Z方向的受力;Step 1, set tension sensors on the upper beam, lower beam, left beam, right beam and connecting parts of the frame, the tension sensors set on the upper beam and the lower beam measure the force of the in-line fittings in the Y direction; The tension sensors arranged on the left beam and the right beam measure the force of the in-line fittings in the X direction; the tension sensors arranged in the connecting part measure the force of the in-line fittings in the Z direction;

步骤2,将变压器高压套管端部一字型金具静态拉力测量系统设置在一字型金具上,由拉力传感器检测一字型金具的受力情况,获取拉力参数值;Step 2. Set the static tension measurement system of the inline fittings at the end of the high-voltage bushing of the transformer on the inline fittings, and use the tension sensor to detect the stress of the inline fittings to obtain the tension parameter value;

步骤3,输出各个传感器获取的拉力参数值,将拉力传感器按照X方向、Y方向、Z方向的分类,对测量X方向、Y方向、Z方向受力的拉力传感器分别求取平均值,得到一字型金具在X方向、Y方向、Z方向的拉力参数值;Step 3, output the tension parameter values obtained by each sensor, classify the tension sensors according to the X direction, Y direction, and Z direction, and calculate the average value of the tension sensors that measure the force in the X direction, Y direction, and Z direction respectively, and obtain a The tensile parameter values of the font fittings in the X direction, Y direction and Z direction;

步骤4,将输出的拉力参数值与预设的拉力参数值进行比较,若超出预设的最大拉力参数值,则进行报警,并发送报警信息;若未超出预设的最大拉力参数值,则继续检测,执行步骤2。Step 4, compare the output pulling force parameter value with the preset pulling force parameter value, if it exceeds the preset maximum pulling force parameter value, an alarm will be issued and an alarm message will be sent; if the preset maximum pulling force parameter value is not exceeded, then Continue testing and go to step 2.

该实施例中,除了可以实时检测到一字型金具的拉力值外,还可通过采集的拉力值判断一字型金具的使用状况,当金具可能发生断裂时,发送报警信息,能够及时发现并进行更换或检修。例如,金具所能承受的最大的力是100N,则预设的最大拉力参数值为100N,若采用的拉力参数值大于100N时,金具超出了最大承受力,可能发生断裂,此时发送报警信息进行报警,通过检修人员到现场进行检修或更换。In this embodiment, in addition to real-time detection of the pulling force value of the straight fittings, the usage status of the straight fittings can also be judged through the collected pulling force values, and when the fittings may break, an alarm message can be sent, which can be found and repaired in time. Replace or overhaul. For example, if the maximum force that the fittings can bear is 100N, the preset maximum tension parameter value is 100N. If the value of the tension parameter is greater than 100N, the fitting exceeds the maximum bearing force and may break, and an alarm message will be sent at this time An alarm is issued, and maintenance personnel are sent to the scene for maintenance or replacement.

在一个实施例中,本发明包括如下步骤:In one embodiment, the present invention comprises the steps of:

步骤1,在框体的上横梁、下横梁、左横梁、右横梁及连接部均设置拉力传感器,所述上横梁与下横梁设置的拉力传感器测量一字型金具在Y方向的受力;所述左横梁与右横梁设置的拉力传感器测量一字型金具在X方向的受力;所述连接部内设置的拉力传感器测量一字型金具在Z方向的受力;Step 1, set tension sensors on the upper beam, lower beam, left beam, right beam and connecting parts of the frame, the tension sensors set on the upper beam and the lower beam measure the force of the in-line fittings in the Y direction; The tension sensors arranged on the left beam and the right beam measure the force of the in-line fittings in the X direction; the tension sensors arranged in the connecting part measure the force of the in-line fittings in the Z direction;

步骤2,将变压器高压套管端部一字型金具静态拉力测量系统设置在一字型金具上,由拉力传感器检测一字型金具的受力情况,获取拉力参数值;Step 2. Set the static tension measurement system of the inline fittings at the end of the high-voltage bushing of the transformer on the inline fittings, and use the tension sensor to detect the stress of the inline fittings to obtain the tension parameter value;

步骤3,输出各个传感器获取的拉力参数值,将拉力传感器按照X方向、Y方向、Z方向的分类,对测量X方向、Y方向、Z方向受力的拉力传感器分别求取平均值,得到一字型金具在X方向、Y方向、Z方向的拉力参数值;Step 3, output the tension parameter values obtained by each sensor, classify the tension sensors according to the X direction, Y direction, and Z direction, and calculate the average value of the tension sensors that measure the force in the X direction, Y direction, and Z direction respectively, and obtain a The tensile parameter values of the font fittings in the X direction, Y direction and Z direction;

步骤4,将输出的拉力参数值与预设的拉力参数值进行比较,若超出预设的最大拉力参数值,则进行报警,并发送报警信息;若未超出预设的最大拉力参数值,则继续检测,执行步骤2;Step 4, compare the output pulling force parameter value with the preset pulling force parameter value, if it exceeds the preset maximum pulling force parameter value, an alarm will be issued and an alarm message will be sent; if the preset maximum pulling force parameter value is not exceeded, then Continue to detect, go to step 2;

步骤5,获取变压器高压套管端部一字型金具所处的位置信息,在发送报警信息的同时发送位置信息。Step 5: Obtain the location information of the inline fittings at the end of the high voltage bushing of the transformer, and send the location information while sending the alarm information.

该实施例中,在判断出一字型金具可能发生断裂,发送报警信息时,同时获取该金具的位置信息并发送,以便检修人员能够快速查找故障位置,到现场进行维护。该方法解决了现有变电站变压器套管端部接线金具横向受力实际情况的检测难问题,避免了当金具横向受力过大可能发生断裂时,因不能够及时发现、进行检修或更换导致主变发生匝间短路故障的问题;本发明方便了检修和测试工作,降低了人力成本。In this embodiment, when it is judged that the inline fitting may break and the alarm message is sent, the position information of the fitting is acquired and sent at the same time, so that maintenance personnel can quickly find the location of the fault and carry out maintenance on site. This method solves the difficult problem of detecting the actual situation of the horizontal force of the fittings at the end of the transformer bushing in the existing substation, and avoids the possibility of breaking the fittings due to the failure to detect, repair or replace them in time when the fittings are subjected to excessive lateral force. The problem of inter-turn short-circuit fault is changed; the invention facilitates maintenance and testing work, and reduces labor costs.

该方法能够实时检测一字型金具的受力情况,当获取的拉力参数值大于预设的最大值时,判断一字型金具可能发生断裂,将报警信息和位置信息发送给监控中心,监控中心记录后派出检修人员到现场检修。也可同时给检修人员发送报警短信或发送到检修人员的手机APP上,检修人员到现场检修后将处理情况反馈给监控中心,由监控中心记录。This method can detect the stress of the straight fittings in real time. When the obtained tensile parameter value is greater than the preset maximum value, it is judged that the straight fittings may break, and the alarm information and location information are sent to the monitoring center. After recording, send maintenance personnel to the scene for maintenance. It can also send an alarm message to the maintenance personnel at the same time or send it to the mobile phone APP of the maintenance personnel. After the maintenance personnel go to the site for maintenance, they will feed back the processing situation to the monitoring center, and the monitoring center will record it.

在一个实施例中,当获取的拉力参数值大于预设的最大值时,判断一字型金具可能发生断裂,将报警信息和位置信息发送给监控中心,监控中心记录后派出检修人员到现场检修。也可同时给检修人员发送报警短信或发送到检修人员的手机APP上,检修人员到现场检修后将处理情况反馈给监控中心,由监控中心记录。In one embodiment, when the obtained tensile parameter value is greater than the preset maximum value, it is judged that the inline fitting may break, and the alarm information and location information are sent to the monitoring center, and the monitoring center sends maintenance personnel to the site for maintenance after recording . It can also send an alarm message to the maintenance personnel at the same time or send it to the mobile phone APP of the maintenance personnel. After the maintenance personnel go to the site for maintenance, they will feed back the processing situation to the monitoring center, and the monitoring center will record it.

在一个实施例中,当获取的拉力参数值小于预设的最大值时,进一步判断是否在第二预设值范围内,例如,当一字型金具承受的拉力大于100N时会发生断裂,当它承受的拉力值长时间处理90-99N时,当时间达到一定节点时,例如100h时,或达到一定的次数时,易发生损坏或断裂。若获取的拉力参数值在第二预设值范围内时,记录发生的时间、拉力参数值后,继续检测。若获取的拉力参数值在第二预设值范围内超出预设的时间或次数时,发出预警信息,并同时发送位置信息,通知检修人员到现场维护。本实施例的方法可进一步判断金具的使用状况,能够及时发现问题,避免因金具断裂造成的跳闸现象。In one embodiment, when the obtained tensile force parameter value is less than the preset maximum value, it is further judged whether it is within the second preset value range, for example, when the pull force of the inline fitting is greater than 100N, it will break, and when When the tension value it bears is 90-99N for a long time, when the time reaches a certain node, such as 100h, or reaches a certain number of times, it is easy to be damaged or broken. If the acquired tension parameter value is within the second preset value range, record the occurrence time and the tension parameter value, and then continue detection. If the obtained tension parameter value exceeds the preset time or times within the second preset value range, an early warning message is sent, and at the same time location information is sent to notify maintenance personnel to go to the site for maintenance. The method of this embodiment can further judge the use status of the fittings, and can detect problems in time to avoid tripping caused by the breakage of the fittings.

最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其他修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solution of the present invention without limitation, other modifications or equivalent replacements made by those skilled in the art to the technical solution of the present invention, as long as they do not depart from the spirit and spirit of the technical solution of the present invention All should be included in the scope of the claims of the present invention.

Claims (10)

1. a transformer high-voltage bushing end yi word pattern gold utensil static tensile force measures system, it is characterised in that: include framework, institute Stating framework and include entablature, sill, left crossbeam and right crossbeam, entablature and the sill of described framework set the most in the horizontal direction Putting two holes, be provided with middle cross beam in the middle part of described framework, wherein the middle cross beam arranges two holes in the horizontal direction, described entablature, Middle cross beam is corresponding at vertical direction with the hole of sill;Wherein the middle cross beam includes fixed part and two connecting portions, described fixed part Two ends are arranged in framework through connecting portion, and the top of described fixed part is in the horizontal direction higher than described entablature and sill, the end Portion is in the horizontal direction less than described entablature and sill;Described entablature, sill, left crossbeam, right crossbeam and connecting portion are equal It is provided with pulling force sensor.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature It is: described each connecting portion is provided with pulling force sensor.
3. according to claim 1 or the 2 transformer high-voltage bushing end yi word pattern gold utensil static tensile force stated measure systems, it is special Levying and be: arrange four pulling force sensors in described connecting portion, four described pulling force sensors are evenly distributed on connecting portion Surrounding.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature Being: be equipped with two grooves on described entablature, sill, left crossbeam and right crossbeam, described pulling force sensor is arranged on recessed In groove.
Transformer high-voltage bushing end the most according to claim 4 yi word pattern gold utensil static tensile force measures system, its feature It is: in described groove, two pulling force sensors are set at vertical direction.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature It is: two holes being equipped with inside projection, described entablature and sill on described entablature and sill are respectively provided at On corresponding projection.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature It is: the thickness of described connecting portion is less than described framework.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature It is: described transformer high-voltage bushing end yi word pattern gold utensil static tensile force is measured system and also included digital display meter, described digital display meter Being connected with the binding post arranged in framework, described binding post electrically connects with pulling force sensor.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measures system, its feature It is: described transformer high-voltage bushing end yi word pattern gold utensil static tensile force is measured system and also included power supply, described power supply and frame The binding post arranged on body connects, and described binding post electrically connects with pulling force sensor.
Transformer high-voltage bushing end the most according to claim 1 yi word pattern gold utensil static tensile force measuring method, its feature It is: comprise the steps:
Step 1, entablature, sill, left crossbeam, right crossbeam and the connecting portion in framework is respectively provided with pulling force sensor, described on The pulling force sensor that crossbeam and sill are arranged measures yi word pattern gold utensil stress in the Y direction;Described left crossbeam sets with right crossbeam The pulling force sensor put measures the yi word pattern gold utensil stress in X-direction;The pulling force sensor arranged in described connecting portion measures one Font gold utensil is in the stress of Z-direction;
Step 2, is arranged on transformer high-voltage bushing end yi word pattern gold utensil static tensile force measurement system on yi word pattern gold utensil, by The stressing conditions of pulling force sensor detection yi word pattern gold utensil, obtains pulling force parameter value;
Step 3, exports the pulling force parameter value that each sensor obtains, to the pulling force biography measuring X-direction, Y-direction, Z-direction stress Sensor averaged respectively, obtains yi word pattern gold utensil at X-direction, Y-direction, the pulling force parameter value of Z-direction.
CN201610687972.1A 2016-08-19 2016-08-19 System and method for measuring static tension of straight-line-shaped hardware fitting at end part of high-voltage sleeve of transformer Active CN106323524B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610687972.1A CN106323524B (en) 2016-08-19 2016-08-19 System and method for measuring static tension of straight-line-shaped hardware fitting at end part of high-voltage sleeve of transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610687972.1A CN106323524B (en) 2016-08-19 2016-08-19 System and method for measuring static tension of straight-line-shaped hardware fitting at end part of high-voltage sleeve of transformer

Publications (2)

Publication Number Publication Date
CN106323524A true CN106323524A (en) 2017-01-11
CN106323524B CN106323524B (en) 2021-10-26

Family

ID=57744082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610687972.1A Active CN106323524B (en) 2016-08-19 2016-08-19 System and method for measuring static tension of straight-line-shaped hardware fitting at end part of high-voltage sleeve of transformer

Country Status (1)

Country Link
CN (1) CN106323524B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110530566A (en) * 2019-10-10 2019-12-03 国网河南省电力公司电力科学研究院 A circuit breaker opening and closing spring pressure monitoring system and detection method
CN111829711A (en) * 2019-03-29 2020-10-27 新东工业株式会社 Force sensor

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB8720340D0 (en) * 1987-08-28 1987-10-07 Gen Electric Co Plc Three-dimensional structure
WO1988008521A1 (en) * 1987-04-24 1988-11-03 Kabushiki Kaisha Nexy Kenkyusho Force and moment detector using resistor
US5490427A (en) * 1994-10-17 1996-02-13 Fanuc Usa Corporation Six axis force sensor employing multiple shear strain gages
CN1916579A (en) * 2006-09-11 2007-02-21 东华大学 2D force sensor of dynamic friction testing for fabric
US20090229378A1 (en) * 2007-07-03 2009-09-17 Kulite Semiconductor Products, Inc. Joystick sensor apparatus
CN102095534A (en) * 2010-12-08 2011-06-15 上海交通大学 Double rood beam high-sensitivity six-dimensional moment sensor
US20110314935A1 (en) * 2009-02-06 2011-12-29 Abb Ag Set of multiaxial force and torque sensor and assembling method
US20150135856A1 (en) * 2012-05-10 2015-05-21 Korea Electronics Technology Institute Force torque sensor, force torque sensor frame, and force torque measurement method
CN206074164U (en) * 2016-08-19 2017-04-05 国网河南省电力公司电力科学研究院 Transformer high-voltage bushing end yi word pattern gold utensil three-dimensional pulling force sensor

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1988008521A1 (en) * 1987-04-24 1988-11-03 Kabushiki Kaisha Nexy Kenkyusho Force and moment detector using resistor
GB8720340D0 (en) * 1987-08-28 1987-10-07 Gen Electric Co Plc Three-dimensional structure
US5490427A (en) * 1994-10-17 1996-02-13 Fanuc Usa Corporation Six axis force sensor employing multiple shear strain gages
CN1916579A (en) * 2006-09-11 2007-02-21 东华大学 2D force sensor of dynamic friction testing for fabric
US20090229378A1 (en) * 2007-07-03 2009-09-17 Kulite Semiconductor Products, Inc. Joystick sensor apparatus
US20110314935A1 (en) * 2009-02-06 2011-12-29 Abb Ag Set of multiaxial force and torque sensor and assembling method
CN102095534A (en) * 2010-12-08 2011-06-15 上海交通大学 Double rood beam high-sensitivity six-dimensional moment sensor
US20150135856A1 (en) * 2012-05-10 2015-05-21 Korea Electronics Technology Institute Force torque sensor, force torque sensor frame, and force torque measurement method
CN206074164U (en) * 2016-08-19 2017-04-05 国网河南省电力公司电力科学研究院 Transformer high-voltage bushing end yi word pattern gold utensil three-dimensional pulling force sensor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111829711A (en) * 2019-03-29 2020-10-27 新东工业株式会社 Force sensor
CN110530566A (en) * 2019-10-10 2019-12-03 国网河南省电力公司电力科学研究院 A circuit breaker opening and closing spring pressure monitoring system and detection method

Also Published As

Publication number Publication date
CN106323524B (en) 2021-10-26

Similar Documents

Publication Publication Date Title
CN112666433A (en) Cable accessory insulation composite interface breakdown voltage testing device
CN118376897B (en) Cable GIS terminal performance test system and method
CN118465456B (en) Switch cabinet sensor layout optimization method and system
CN206074164U (en) Transformer high-voltage bushing end yi word pattern gold utensil three-dimensional pulling force sensor
CN111426412A (en) An annular stress sensing device and detection method suitable for GIL three-pillar insulators
CN106771665A (en) A kind of gas insulated bus junction contacts condition checkout gear and method
CN107765116A (en) A kind of on-line monitoring method for cable termination on-Line Monitor Device
CN106323524A (en) Transformer high voltage bushing end linear metal fitting static state pulling force measurement system and method
CN108871449A (en) A kind of transmission line online monitoring system with electric field monitoring
CN109238681A (en) Fuse switch detection system and method
CN206114165U (en) Perpendicular force sensor of transformer high -tension bushing tip goat's horn type gold utensil
CN209690353U (en) Combined arrester leakage current measurement device
CN106124111B (en) Transformer high-voltage bushing end goat's horn type gold utensil static tensile force measuring system and method
CN206114168U (en) Three -dimensional force sensor of transformer high -tension bushing tip goat's horn type gold utensil
CN110793763A (en) A GIL equipment three-pillar insulator column leg insert bonding strength test system
CN206074163U (en) Transformer high-voltage bushing end yi word pattern gold utensil vertical tension sensor
CN206114169U (en) Transformer high -tension bushing tip goat's horn type gold utensil axial tension sensor
CN119470074A (en) A mechanical swing test device and method for insulator
CN206074154U (en) Transformer high-voltage bushing end yi word pattern gold utensil axial tension sensor
CN206114166U (en) A transformer high -tension bushing tip style of calligraphy gold utensil lateral pull sensor
CN206114167U (en) Transformer high -tension bushing tip goat's horn type gold utensil lateral pull sensor
CN105403787A (en) Simulation apparatus for local overheating defect in composite apparatus
CN203838228U (en) Spherical voltage sensor
CN106644199A (en) Real-time signal monitoring system-based electrodynamic force experimental measurement method
CN113410797B (en) Strain clamp crimping monitoring method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant